Square Feet of Space Machine Number of Hours Material Moves Machining Assembly Total 80,000 20,000 90,000 80,000 40,000 120,000 60,000 100,000 150,000 Eater Cell Edger Cell Direct materials S185,000 S1,140,000 Direct labor 66,000 99,000 660,000 350,500 Direct overhead Allocated overhead* 75,000 75,000 Total $425,000 $2,225,500 *Building and grounds are allocated on the basis of square footage.

Survey of Accounting (Accounting I)
8th Edition
ISBN:9781305961883
Author:Carl Warren
Publisher:Carl Warren
Chapter11: Cost-volume-profit Analysis
Section: Chapter Questions
Problem 11.18E
icon
Related questions
Question

Mott Company recently implemented a JIT manufacturing system. After one year of operation,Heidi Burrows, president of the company, wanted to compare product cost under the JIT system
with product cost under the old system. Mott’s two products are weed eaters and lawn edgers. The unit prime costs under the old system are as follows:

                                Eaters   Edgers
Direct materials         $12      $45
Direct labor                   4        30

Under the old manufacturing system, the company operated three service centers and two pro-
duction departments. Overhead was applied using departmental overhead rates. The direct over-
head costs associated with each department for the year preceding the installation of JIT are as

follows:

Maintenance              $110,000
Materials handling      90,000
Building and grounds 150,000
Machining                   280,000
Assembly                     175,000
Total                            $805,000

the producing departments and then to the products passing through them. (Both products passed through each producing department.) The overhead rate for the Machining Department
was based on machine hours, and the overhead rate for assembly was based on direct labor hours. During the last year of operations for the old system, the Machining Department used
80,000 machine hours, and the Assembly Department used 20,000 direct labor hours. Each weed eater required 1.0 machine hour in Machining and 0.25 direct labor hour in Assembly. Each lawn edger required 2.0 machine hours in Machining and 0.5 hour in Assembly. Bases for allocation of the service costs are as follows:

Upon implementing JIT, a manufacturing cell for each product was created to replace the departmental structure. Each cell occupied 40,000 square feet. Maintenance and materials han-
dling were both decentralized to the cell level. Essentially, cell workers were trained to operate the machines in each cell, assemble the components, maintain the machines, and move the partially completed units from one point to the next within the cell. During the first year of the JIT system, the company produced and sold 20,000 weed eaters and 30,000 lawn edgers. This output was identical to that for the last year of operations under the old system. The following costs have been assigned to the manufacturing cells:

1. Compute the unit cost for each product under the old manufacturing system.
2. Compute the unit cost for each product under the JIT system.
3. Which of the unit costs is more accurate? Explain. Include in your explanation a discussion
of how the computational approaches differ.
4. Calculate the decrease in overhead costs under JIT, and provide some possible reasons that
explain the decrease.

Square Feet
of Space
Machine
Number of
Hours
Material Moves
Machining
Assembly
Total
80,000
20,000
90,000
80,000
40,000
120,000
60,000
100,000
150,000
Transcribed Image Text:Square Feet of Space Machine Number of Hours Material Moves Machining Assembly Total 80,000 20,000 90,000 80,000 40,000 120,000 60,000 100,000 150,000
Eater Cell
Edger Cell
Direct materials
S185,000
S1,140,000
Direct labor
66,000
99,000
660,000
350,500
Direct overhead
Allocated overhead*
75,000
75,000
Total
$425,000
$2,225,500
*Building and grounds are allocated on the basis of square footage.
Transcribed Image Text:Eater Cell Edger Cell Direct materials S185,000 S1,140,000 Direct labor 66,000 99,000 660,000 350,500 Direct overhead Allocated overhead* 75,000 75,000 Total $425,000 $2,225,500 *Building and grounds are allocated on the basis of square footage.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 8 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Survey of Accounting (Accounting I)
Survey of Accounting (Accounting I)
Accounting
ISBN:
9781305961883
Author:
Carl Warren
Publisher:
Cengage Learning