Spencer manages a store that sells speakers. Each Master Blaster takes 36 hours to create the plastic pieces, 17 hours to create the electronics, and 33 hours of labor to assemble the final product. Each Jammer requires 12 hours to create the plastic pieces, 34 hours to create the electronics, and 39 hours of labor to assemble the final product. The factory has 3060 hours to create the plastic pieces, 2924 hours to create the electronics, and 3813 hours of labor to assemble the final product each week. If each Master Blaster generates $3 in revenue, and each Jammer generates $11, how many of each of the speakers should Spencer have the store sell each week to make the most revenue? Master Blaster: Jammer: Best revenue:
Spencer manages a store that sells speakers. Each Master Blaster takes 36 hours to create the plastic pieces, 17 hours to create the electronics, and 33 hours of labor to assemble the final product. Each Jammer requires 12 hours to create the plastic pieces, 34 hours to create the electronics, and 39 hours of labor to assemble the final product. The factory has 3060 hours to create the plastic pieces, 2924 hours to create the electronics, and 3813 hours of labor to assemble the final product each week. If each Master Blaster generates $3 in revenue, and each Jammer generates $11, how many of each of the speakers should Spencer have the store sell each week to make the most revenue?
Master Blaster:
Jammer:
Best revenue:
Step by step
Solved in 2 steps