Solve the quations: Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information. Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks. The question is : Create a risk register for the project. Identify six potential risks, including risks related to the problems described in the previous paragraph. Include negative and positive risks.

Accounting Information Systems
10th Edition
ISBN:9781337619202
Author:Hall, James A.
Publisher:Hall, James A.
Chapter15: Auditing It Controls Part Ii: Security And Access
Section: Chapter Questions
Problem 2P
icon
Related questions
Question
Solve the quations: Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information. Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks. The question is : Create a risk register for the project. Identify six potential risks, including risks related to the problems described in the previous paragraph. Include negative and positive risks.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,