Situation XXV: A 4-m long pipe having a diameter of 600 mm is to beinstalled. The installation can be done in one our by a group of workersconsisting of 1 foreman, 2 skilled workers, and 10 unskilled workers. Theforeman is paid P50.00 per hour, each skilled workers at P40.00 per hour, andeach unskilled workers at P35.00 per hour. A backhoe is to be rented forP800.00 per hor and a plate compactor for P120.00 per hour. For every meterof pipe, the materials to be used are 0.07 bags of cement at P130.00 per bagand 0.15m3of sand at P300.00 per m3. The cost of pipe is P570.00 per meter.Profit, overhead, insurance, and miscellaneous expense is 30% of the labor,materials, and equipment cost. The value added tax is 10% o the labor andmaterial cost.73. 1.Which of the following most nearly gives the cost of labor and equipment ment per meter length of pipe? A.P120.00/m3 B.P350.00/m3 C.P1,400.00/m3 D.P480.00/m374   2.Which of the following most nearly gives the cost of materials per length of pipe.  A 1267.1 B.1320.45 C.1327.74 D. 1420.74

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Situation XXV: A 4-m long pipe having a diameter of 600 mm is to beinstalled. The installation can be done in one our by a group of workersconsisting of 1 foreman, 2 skilled workers, and 10 unskilled workers. Theforeman is paid P50.00 per hour, each skilled workers at P40.00 per hour, andeach unskilled workers at P35.00 per hour. A backhoe is to be rented forP800.00 per hor and a plate compactor for P120.00 per hour. For every meterof pipe, the materials to be used are 0.07 bags of cement at P130.00 per bagand 0.15m3of sand at P300.00 per m3. The cost of pipe is P570.00 per meter.Profit, overhead, insurance, and miscellaneous expense is 30% of the labor,materials, and equipment cost. The value added tax is 10% o the labor andmaterial cost.73.
1.Which of the following most nearly gives the cost of labor and equipment ment per meter length of pipe?
A.P120.00/m3
B.P350.00/m3
C.P1,400.00/m3
D.P480.00/m374
 
2.Which of the following most nearly gives the cost of materials per length of pipe. 
A 1267.1
B.1320.45
C.1327.74
D. 1420.74
 
 
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Basics of life cycle costing
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning