Shredder Manufacturing has the following projected unit sales (at $18 per unit) for four months of operations: Month Unit Sales January 60,000 February 72,000 March 76,800 April 84,000 Twenty-five percent of the customers are expected to pay in the month of sale and take a 3 percent discount; 70 percent of the customers are expected to pay in the month following sale. The remaining 5 percent will never pay. It takes two pounds of raw material (costing $0.75 per pound) to produce a unit of product. In January, no raw material is in beginning inventories, but management wants to end each month with enough material for 20 percent of the next month’s production. (April’s production is assumed to be 81,600 units.) Shredder Manufacturing pays for 60 percent of its material purchases in the month of purchase and 40 percent in the following month. Each unit of product requires 0.5 hours of labor time. Labor is paid $15 per hour and is paid in the same month as worked. Overhead is estimated to be $2 per unit plus $60,000 per month (including depreciation of $28,800). Overhead costs are paid as incurred. Shredder will begin January with no Work in Process or Finished Goods Inventory. Inventory policy for these two accounts is set at zero ending WIP and 25 percent of the following month’s sales for FG. Note: Do not use negatives signs in any of the schedules below. d. Prepare a direct labor budget for January, February, and March. Jan. Feb. March Total Production Answer Answer Answer Answer DL time per unit Answer Answer Answer Answer DLHs Answer Answer Answer Answer DL rate Answer Answer Answer Answer DL cost Answer Answer Answer Answer e. Prepare an overhead budget for January, February, and March. Jan. Feb. March Total Production Answer Answer Answer Answer VOH unit rate Answer Answer Answer Answer Total VOH Answer Answer Answer Answer FOH cost Answer Answer Answer Answer Total OH Answer Answer Answer Answer f. Prepare a cash receipts schedule for sales and a cash payments schedule for material purchased. Cash Receipts Schedule Jan. Feb. March Total Jan. Answer Answer Answer Answer Feb. Answer Answer Answer Answer March Answer Answer Answer Answer Total Answer Answer Answer Answer Cash Payments Schedule Jan. Feb. March Total Jan. Answer Answer Answer Answer Feb. Answer Answer Answer Answer March Answer Answer Answer Answer Total Answer Answer Answer Answer
Oh no! Our expert couldn't answer your question.
Don't worry! We won't leave you hanging. Plus, we're giving you back one question for the inconvenience.
Here's what the expert had to say:
Comprehensive budgets
Shredder Manufacturing has the following projected unit sales (at $18 per unit) for four months of operations:
Month | Unit Sales |
---|---|
January | 60,000 |
February | 72,000 |
March | 76,800 |
April | 84,000 |
Twenty-five percent of the customers are expected to pay in the month of sale and take a 3 percent discount; 70 percent of the customers are expected to pay in the month following sale. The remaining 5 percent will never pay.
It takes two pounds of raw material (costing $0.75 per pound) to produce a unit of product. In January, no raw material is in beginning inventories, but management wants to end each month with enough material for 20 percent of the next month’s production. (April’s production is assumed to be 81,600 units.) Shredder Manufacturing pays for 60 percent of its material purchases in the month of purchase and 40 percent in the following month.
Each unit of product requires 0.5 hours of labor time. Labor is paid $15 per hour and is paid in the same month as worked.
Shredder will begin January with no Work in Process or Finished Goods Inventory. Inventory policy for these two accounts is set at zero ending WIP and 25 percent of the following month’s sales for FG.
Note: Do not use negatives signs in any of the schedules below.
d. Prepare a direct labor budget for January, February, and March.
Jan. | Feb. | March | Total | |
---|---|---|---|---|
Production | Answer | Answer | Answer | Answer |
DL time per unit | Answer | Answer | Answer | Answer |
DLHs | Answer | Answer | Answer | Answer |
DL rate | Answer | Answer | Answer | Answer |
DL cost | Answer | Answer | Answer | Answer |
e. Prepare an overhead budget for January, February, and March.
Jan. | Feb. | March | Total | |
---|---|---|---|---|
Production | Answer | Answer | Answer | Answer |
VOH unit rate | Answer | Answer | Answer | Answer |
Total VOH | Answer | Answer | Answer | Answer |
FOH cost | Answer | Answer | Answer | Answer |
Total OH | Answer | Answer | Answer | Answer |
f. Prepare a cash receipts schedule for sales and a cash payments schedule for material purchased.
Cash Receipts Schedule
Jan. | Feb. | March | Total | |
---|---|---|---|---|
Jan. | Answer | Answer | Answer | Answer |
Feb. | Answer | Answer | Answer | Answer |
March | Answer | Answer | Answer | Answer |
Total | Answer | Answer | Answer | Answer |
Cash Payments Schedule
Jan. | Feb. | March | Total | |
---|---|---|---|---|
Jan. | Answer | Answer | Answer | Answer |
Feb. | Answer | Answer | Answer | Answer |
March | Answer | Answer | Answer | Answer |
Total | Answer | Answer | Answer | Answer |
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 4 images