Sheridan Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Splish Structures Ltd. The contract is a non-cancellable fixed-price contract for $10 million. The following data pertain to the construction period (all figures in thousands). Costs for the year Estimated costs to complete Progress billings for the year (non-refundable) Cash collected for the year 2023 2024 2025 $3,820 4,675 1,165 4,675 1,235 0 3,460 3,130 4,170 2.570 4,220 2,850 The construction industry has experienced significant expansion, making construction materials and labour more costly than originally estimated. Sheridan finds it extremely difficult to estimate the costs to complete construction and therefore difficult to estimate the percentage complete. It must account for the construction project using the zero-profit method.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Sheridan Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Splish Structures Ltd.
The contract is a non-cancellable fixed-price contract for $10 million. The following data pertain to the construction period (all figures
in thousands).
2023
$3,820
4,675 1,235
Costs for the year
Estimated costs to complete
Progress billings for the year (non-refundable) 3,460
Cash collected for the year
3,130
2024
2025
4,675 1.165
4,170
0.
2,570
4,220 2,850
The construction industry has experienced significant expansion, making construction materials and labour more costly than originally
estimated. Sheridan finds it extremely difficult to estimate the costs to complete construction and therefore difficult to estimate the
percentage complete. It must account for the construction project using the zero-profit method.
Transcribed Image Text:Sheridan Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Splish Structures Ltd. The contract is a non-cancellable fixed-price contract for $10 million. The following data pertain to the construction period (all figures in thousands). 2023 $3,820 4,675 1,235 Costs for the year Estimated costs to complete Progress billings for the year (non-refundable) 3,460 Cash collected for the year 3,130 2024 2025 4,675 1.165 4,170 0. 2,570 4,220 2,850 The construction industry has experienced significant expansion, making construction materials and labour more costly than originally estimated. Sheridan finds it extremely difficult to estimate the costs to complete construction and therefore difficult to estimate the percentage complete. It must account for the construction project using the zero-profit method.
Account Titles and Explanation
Construction in Process
Materials, Cash, Payable
(To record cost of construction)
Accounts Receivable
Billings on Construction in Process
(To record progress billings)
Cash
Accounts Receivable
(To record collections)
Contract Ashet/Liability
Revenue from Long Term Contracts
(To record revenues)
Construction Expenses
Contract Asset/Liability
(To record construction expenses)
Debit
Credit
00 00 00 00 00
Transcribed Image Text:Account Titles and Explanation Construction in Process Materials, Cash, Payable (To record cost of construction) Accounts Receivable Billings on Construction in Process (To record progress billings) Cash Accounts Receivable (To record collections) Contract Ashet/Liability Revenue from Long Term Contracts (To record revenues) Construction Expenses Contract Asset/Liability (To record construction expenses) Debit Credit 00 00 00 00 00
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education