Ivanhoe Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Metlock Structures Ltd. The contract is a non-cancellable fixed-price contract for $9.6 million. The following data pertain to the construction period (all figures in thousands). 2023 Costs for the year $3,375 Estimated costs to complete 4.125 Progress billings for the year (non-refundable) 3,050 3,550 3,000 Cash collected for the year 2.685 3,600 3,315 2024 4,125 2025 1.800 1,875 0.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Please help me with all answers thanku 

(b)
Calculate the amount of the gross profit to be recognized each year of the contract. (Enter negative amounts using either a negative
sign preceding the number eg.-45 or parentheses eg. (45).)
Gross profit/(loss)
Save for Later
2023
7
2024
2025
Attempts: 0 of 1udSubmit Awar
(c1)
The parts of this question must be completed in order. This part will be available when you complete the part abo
Transcribed Image Text:(b) Calculate the amount of the gross profit to be recognized each year of the contract. (Enter negative amounts using either a negative sign preceding the number eg.-45 or parentheses eg. (45).) Gross profit/(loss) Save for Later 2023 7 2024 2025 Attempts: 0 of 1udSubmit Awar (c1) The parts of this question must be completed in order. This part will be available when you complete the part abo
Ivanhoe Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Metlock Structures Ltd.
The contract is a non-cancellable fixed-price contract for $9.6 million. The following data pertain to the construction period (all figures
in thousands).
Costs for the year
Estimated costs to complete
Progress billings for the year (non-refundable)
Cash collected for the year
(a)
2023
$3,375
4,125
3,050
2024
2025
4,125
1,875
3,550 3,000
2,685 3,600
1.800
-0.
3,315
Transcribed Image Text:Ivanhoe Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Metlock Structures Ltd. The contract is a non-cancellable fixed-price contract for $9.6 million. The following data pertain to the construction period (all figures in thousands). Costs for the year Estimated costs to complete Progress billings for the year (non-refundable) Cash collected for the year (a) 2023 $3,375 4,125 3,050 2024 2025 4,125 1,875 3,550 3,000 2,685 3,600 1.800 -0. 3,315
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education