Scenar A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the next is $6. Forecast Beginning Inventory Regular Time Overtime Subcontracting Ending Inventory January 400 100 February 800 March 1200 April 700 May 300 The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five-month window. The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts. Without actually solving the aggregate planning problem, it is safe to conclude that in the optimal solution to Scenario 8.2, Select one: O a. the number of units made using regular time will exceed the forecast. O b. the number of units made using subcontracting will exceed the number of units made using regular time. Oc the total ending inventory will exceed the number of units made using overtime. O d. the number of units made using subcontracting will exceed the number of units made using overtime.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Solve all this question compulsory........

Scenario 8,2 - Willow
A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing
the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the
next is $6.
Forecast
Beginning Inventory
Regular Time
Overtime
Subcontracting
Ending Inventory
January
400
100
February
800
March
1200
April
700
May
300
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five-month window. The plant
capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts.
Without actually solving the aggregate planning problem, it is safe to conclude that in the optimal solution to Scenario 8.2,
Select one:
O a. the number of units made using regular time will exceed the forecast.
O b. the number of units made using subcontracting will exceed the number of units made using regular time.
O c. the total ending inventory will exceed the number of units made using overtime.
O d. the number of units made using subcontracting will exceed the number of units made using overtime.
1
2
4
Für
Transcribed Image Text:Scenario 8,2 - Willow A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the next is $6. Forecast Beginning Inventory Regular Time Overtime Subcontracting Ending Inventory January 400 100 February 800 March 1200 April 700 May 300 The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five-month window. The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts. Without actually solving the aggregate planning problem, it is safe to conclude that in the optimal solution to Scenario 8.2, Select one: O a. the number of units made using regular time will exceed the forecast. O b. the number of units made using subcontracting will exceed the number of units made using regular time. O c. the total ending inventory will exceed the number of units made using overtime. O d. the number of units made using subcontracting will exceed the number of units made using overtime. 1 2 4 Für
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.