Resource levelling: Key: A D Task ID 4 Duration 19 19 12 12 15 15 LST LFT EST EFT Slack 5 5 8 15 7 1 Start H 19 20 3 5 4 19 20 12 11 11 15 3 6 11 11 15 9. End M 20 20 6. 2 5 12 10 2 12 14 14 19 6. 10 12 12 17 2 G K 5 6. 2 18 17 1 18 20 17 19 1 7 12 12 11 1 6 11 In the following 4 questions, we work with the above analysed network and we assume that: • The project must be completed in its optimal time (20 time units) • Each task requires exactly 1 human resource allocated to it. Question: What is the minimum number of people who could be working simultaneously at time t=2? Hint: Look at the EST/EFT/LST/LFT values for tasks which overlap time t=2, i.e. tasks A, B and C. Answer: What is the maximum number of people who could be working simultaneously at time t=2 time units?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

1.

Resource levelling:
Key:
Task ID
Duration
LST LFT
EST EFT
Slack
A
5
3
4
7
12
12
15
15
19
5
15
19
7
P
1
Start
B
19
20
3
5
4
19
20
12
11
11
15
6.
11
11
15
9.
End
F
6
4
2
20
12
12
14
14
19
20
6.
10
10
12
12
17
2
K
N
5
6
2
18
17
7
12
12
18
20
6
11
11
17
19
1
1
In the following 4 questions, we work with the above analysed network and we assume that:
• The project must be completed in its optimal time (20 time units)
• Each task requires exactly 1 human resource allocated to it.
Question: What is the minimum number of people who could be working simultaneously at time t=2? Hint: Look at the
EST/EFT/LST/LFT values for tasks which overlap time t=2, i.e. tasks A, Band C.
Answer:
What is the maximum number of people who could be working simultaneously at time t=2 time units?
Transcribed Image Text:Resource levelling: Key: Task ID Duration LST LFT EST EFT Slack A 5 3 4 7 12 12 15 15 19 5 15 19 7 P 1 Start B 19 20 3 5 4 19 20 12 11 11 15 6. 11 11 15 9. End F 6 4 2 20 12 12 14 14 19 20 6. 10 10 12 12 17 2 K N 5 6 2 18 17 7 12 12 18 20 6 11 11 17 19 1 1 In the following 4 questions, we work with the above analysed network and we assume that: • The project must be completed in its optimal time (20 time units) • Each task requires exactly 1 human resource allocated to it. Question: What is the minimum number of people who could be working simultaneously at time t=2? Hint: Look at the EST/EFT/LST/LFT values for tasks which overlap time t=2, i.e. tasks A, Band C. Answer: What is the maximum number of people who could be working simultaneously at time t=2 time units?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.