requirements Scheduled receipts Projected ending inventory: 4,500 Net requirements Planned receipts Planned orders 10,500 20,000 20,000 20,000 15,500 4500 0 0 4,500 0 6,000 15,500 20000 20000 0 0 10,500 15,500 20000 20000 10500 15500 20000 20000 15500 Construct the material requirements plan for item Speakers (enter your responses as whole numbers). Speakers: Lead Time = 1 week; Minimum order quantity = 15,000 Week 1 2 3 4 5 Gross requirements 21,000 40,000 40,000 40,000 Scheduled receipts Projected ending inventory: 14,500 Net requirements Planned receipts 0 4,500 19000 0 0 15500 15500 0 6 31,000 19000 2000 40000 40000 40000 31000 21000 40000 40000 40000 31000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Gross requirements
Scheduled receipts
Projected ending inventory: 4,500
Net requirements
Planned receipts
Planned orders
4500
0
0
10500
10,500 20,000 20,000 20,000 15,500
0
4,500
0
0
0
6,000 15,500 20000 20000 15500
10,500 15,500 20000 20000 15500
15500 20000 20000 15500 0
Construct the material requirements plan for item Speakers (enter your responses as whole numbers).
Speakers: Lead Time=1 week; Minimum order quantity = 15,000
Week
1
2
3
4
5
Gross requirements
0
21,000 40,000 40,000 40,000
Scheduled receipts
4,500
Projected ending inventory: 14,500
19000
Net requirements
Planned receipts
6
31,000
19000
0
2000
40000 40000 40000
31000
21000 40000 40000 40000 31000
Transcribed Image Text:Gross requirements Scheduled receipts Projected ending inventory: 4,500 Net requirements Planned receipts Planned orders 4500 0 0 10500 10,500 20,000 20,000 20,000 15,500 0 4,500 0 0 0 6,000 15,500 20000 20000 15500 10,500 15,500 20000 20000 15500 15500 20000 20000 15500 0 Construct the material requirements plan for item Speakers (enter your responses as whole numbers). Speakers: Lead Time=1 week; Minimum order quantity = 15,000 Week 1 2 3 4 5 Gross requirements 0 21,000 40,000 40,000 40,000 Scheduled receipts 4,500 Projected ending inventory: 14,500 19000 Net requirements Planned receipts 6 31,000 19000 0 2000 40000 40000 40000 31000 21000 40000 40000 40000 31000
Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit.
These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level
O kits. Complete the MRP records, using the following information:
• Production plans for complete kits are as follows:
Start assembling 10,500 kits in week 2
Start assembling 20,000 kits in weeks 3, 4, and 5
Start assembling 15,500 kits in week 6
• The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out
the gross requirements.
• All scheduled receipts, lead times, and beginning inventory levels are shown.
Click the icon to view the MRP records.
Construct the material requirements plan for item System unit (enter your responses as whole numbers).
System unit: Lead Time = 1 week; Minimum order quantity = 10,500
Week
1
Gross requirements
Scheduled receipts
5
2
3
4
10,500 20,000 20,000 20,000
6
15,500
Transcribed Image Text:Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level O kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 10,500 kits in week 2 Start assembling 20,000 kits in weeks 3, 4, and 5 Start assembling 15,500 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 10,500 Week 1 Gross requirements Scheduled receipts 5 2 3 4 10,500 20,000 20,000 20,000 6 15,500
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.