Required information [The following information applies to the questions displayed below.] Marco Company shows the following costs for three jobs worked on in April. Balances on March 31 Direct materials used (in March) Direct labor used (in March) Overhead applied (March) Costs during April Direct materials used Direct labor used Overhead applied Status on April 30 Additional Information Job 306 $ 35,800 26,800 16,800 152,000 91,800 ? Finished (sold) Job 307 $ 41,800 24,800 15,800 237,000 167,000 ? Finished. (unsold) Job 308 $ 117,000 122,000 In process a. Raw Materials Inventory has a March 31 balance of $86,800. b. Raw materials purchases in April are $517,000, and total factory payroll cost in April is $380,000. c. Actual overhead costs incurred in April are indirect materials, $54,250; indirect labor, $27,250; factory rent, $36,250; factory utilities, $23,250; and factory equipment depreciation, $55,250. d. Predetermined overhead rate is 50% of direct labor cost. e. Job 306 is sold for $652,000 cash in April.
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Please do not give solution in image format thanku
![!
Required information
[The following information applies to the questions displayed below.]
Marco Company shows the following costs for three jobs worked on in April.
Balances on March 31
Direct materials used (in March)
Direct labor used (in March)
Overhead applied (March)
Costs during April
Direct materials used
Direct labor used
Overhead applied
Status on April 30
Additional Information
Job 306
Predetermined overhead rate
Overhead applied
$ 35,800
26,800
16,800
306
152,000
91,800
?
Finished
(sold)
Required:
1. Determine the amount of overhead applied to each job in April.
Job 307
307
$ 41,800
24,800
15,800
237,000
167,000
?
Finished
(unsold)
a. Raw Materials Inventory has a March 31 balance of $86,800.
b. Raw materials purchases in April are $517,000, and total factory payroll cost in April is $380,000.
c. Actual overhead costs incurred in April are indirect materials, $54,250; indirect labor, $27,250; factory rent, $36,250;
factory utilities, $23,250; and factory equipment depreciation, $55,250.
d. Predetermined overhead rate is 50% of direct labor cost.
e. Job 306 is sold for $652,000 cash in April.
Job 308
308
$ 117,000
122,000
?
In process
April Total
$
0](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F717ad7aa-6db6-4680-8ef2-b7afe96da5d8%2F2dae2707-3ccd-4465-9ad9-1fb90641aeb8%2Fwz01k5e_processed.png&w=3840&q=75)


Trending now
This is a popular solution!
Step by step
Solved in 3 steps