Operation Number Queue Time (days) Work Operation Time (days) Arrival Finish Center Date Date (a.m.) (р.m.) 10 110 3 20 120 3 30 130 3 Stores 200

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.5: Shortest Path Models
Problem 30P
icon
Related questions
icon
Concept explainers
Topic Video
Question

. Back schedule the following shop order. All times are given in days. Move time
between operations is 1 day, and wait time is 1 day. Due date is day 200. Assume
orders start at the beginning of a day and finish at the end of a day.

Operation
Number
Queue Time
(days)
Work
Operation
Time (days)
Arrival
Finish
Center
Date
Date
(a.m.)
(р.m.)
10
110
3
20
120
3
30
130
3
Stores
200
Transcribed Image Text:Operation Number Queue Time (days) Work Operation Time (days) Arrival Finish Center Date Date (a.m.) (р.m.) 10 110 3 20 120 3 30 130 3 Stores 200
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L