QUESTION 4 (25 marks) Cashave is responsible for developing a training programme for one major deliverable of the ASP Project. The following table shows the relationships between the activities that must be completed, along with estimates of the durations in days and other relevant information such as Activity Variance, Earliest start and finish times, latest start and finish times. Slack Early Early Late Late Variance Critical (Yes/No) Activity Predecessors Duration Start Finish Start Finish A 4.17 0.00 4.17 0.00 4.17 0.69 B A 6.17 4.17 10.34 4.17 10.34 1.36 C A 2.00 4.17 6.17 8.34 10.34 0.11 D B 4.00 10.34 14.34 11.01 15.01 0.44 E B 3.17 10.34 13.51 11.84 15.01 0.25 F B, C 4.17 10.34 14.51 10.34 14.51 0.25 G B 2.17 10.34 12.51 19.84 22.01 0.25 H F 3.00 14.51 17.51 14.51 17.51 0.11 I F, H 1.50 17.51 19.01 17.51 19.01 0.03 J I 3.00 19.01 22.01 19.01 22.01 0.11 K D, E 7.00 14.34 21.34 15.01 22.01 1.00 You are required to assist Cashave in carrying out the following tasks: i. Complete the project schedule above by inserting the Variance and Slack and indicating the critical activities. (6 marks) ii. Prepare a network diagram based on the information in the table above. (5 marks) 111. Identify the activities, which if delayed, will NOT necessarily delay the entire project. (2 marks) iv. Determine the critical path for this project. (4 marks) V. Determine the expected completion time and variance for the project. (4 marks) vi. Cashave, when asked by Monica, advised her that the time in PART (V) as the longest time the project is likely to take. Comment on the accuracy of the information provided by Cashave to Monica. (4 marks)

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

 

Do not use chatgpt

QUESTION 4 (25 marks)
Cashave is responsible for developing a training programme for one major deliverable of the ASP Project.
The following table shows the relationships between the activities that must be completed, along with
estimates of the durations in days and other relevant information such as Activity Variance, Earliest start and
finish times, latest start and finish times.
Slack
Early
Early
Late
Late
Variance
Critical
(Yes/No)
Activity
Predecessors
Duration
Start
Finish
Start Finish
A
4.17
0.00
4.17
0.00
4.17
0.69
B
A
6.17
4.17
10.34
4.17
10.34
1.36
C
A
2.00
4.17
6.17
8.34
10.34
0.11
D
B
4.00
10.34
14.34
11.01
15.01
0.44
E
B
3.17
10.34
13.51
11.84
15.01
0.25
F
B, C
4.17
10.34
14.51
10.34
14.51
0.25
G
B
2.17
10.34
12.51
19.84
22.01
0.25
H
F
3.00
14.51
17.51
14.51
17.51
0.11
I
F, H
1.50
17.51
19.01
17.51
19.01
0.03
J
I
3.00
19.01
22.01
19.01
22.01
0.11
K
D, E
7.00
14.34
21.34
15.01
22.01
1.00
You are required to assist Cashave in carrying out the following tasks:
i. Complete the project schedule above by inserting the Variance and Slack and indicating the critical
activities.
(6 marks)
ii.
Prepare a network diagram based on the information in the table above.
(5 marks)
111.
Identify the activities, which if delayed, will NOT necessarily delay the entire project.
(2 marks)
iv.
Determine the critical path for this project.
(4 marks)
V.
Determine the expected completion time and variance for the project.
(4 marks)
vi.
Cashave, when asked by Monica, advised her that the time in PART (V) as the longest time the project
is likely to take. Comment on the accuracy of the information provided by Cashave to Monica.
(4 marks)
Transcribed Image Text:QUESTION 4 (25 marks) Cashave is responsible for developing a training programme for one major deliverable of the ASP Project. The following table shows the relationships between the activities that must be completed, along with estimates of the durations in days and other relevant information such as Activity Variance, Earliest start and finish times, latest start and finish times. Slack Early Early Late Late Variance Critical (Yes/No) Activity Predecessors Duration Start Finish Start Finish A 4.17 0.00 4.17 0.00 4.17 0.69 B A 6.17 4.17 10.34 4.17 10.34 1.36 C A 2.00 4.17 6.17 8.34 10.34 0.11 D B 4.00 10.34 14.34 11.01 15.01 0.44 E B 3.17 10.34 13.51 11.84 15.01 0.25 F B, C 4.17 10.34 14.51 10.34 14.51 0.25 G B 2.17 10.34 12.51 19.84 22.01 0.25 H F 3.00 14.51 17.51 14.51 17.51 0.11 I F, H 1.50 17.51 19.01 17.51 19.01 0.03 J I 3.00 19.01 22.01 19.01 22.01 0.11 K D, E 7.00 14.34 21.34 15.01 22.01 1.00 You are required to assist Cashave in carrying out the following tasks: i. Complete the project schedule above by inserting the Variance and Slack and indicating the critical activities. (6 marks) ii. Prepare a network diagram based on the information in the table above. (5 marks) 111. Identify the activities, which if delayed, will NOT necessarily delay the entire project. (2 marks) iv. Determine the critical path for this project. (4 marks) V. Determine the expected completion time and variance for the project. (4 marks) vi. Cashave, when asked by Monica, advised her that the time in PART (V) as the longest time the project is likely to take. Comment on the accuracy of the information provided by Cashave to Monica. (4 marks)
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education