Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this project are listed in the table below along with their completion times in weeks. Activity A B с D E F G Normal Time 4 2 3 8 6 3 4 Immediate Predecessor A A A B, D C, E F a. Draw the Network diagram on your own paper. b. What is the critical path and the project's expected completion time? c. If activity B takes an additional 3 weeks, what is impact on the project? d. If activity E takes an additional 1 week, what is impact on the project?
How many paths are there in the network? Enter your response as a number ONLY.
Refer to Problem 2 of the Practice Problems download.
Refer to Problem 2 of the Practice Problems download.
What is the critical path for the network/project?
Refer to Problem 2 of the Practice Problems download.
A-D-E-F-G
A-B-E-F-G
A-C-F-G
A-B-D-C-E-F-G
If activity B takes an additional 3 weeks, what is the impact on the project?
Refer to Problem 2 of the Practice Problems download.
There is no impact on the project duration. Activity B has 6 weeks of slack time.
The entire project will be delayed 3 weeks (28 instead of 25 weeks).
The entire project will be delayed, but it will be less than 3 weeks as Activity B has some slack.
The answer cannot be determined.
If activity E takes an additional 1 weeks, what is the impact on the project?
Refer to Problem 2 of the Practice Problems download.
There is no impact on the project duration. Activity E has slack.
The entire project will take 1 additional week (26 instead of 25 weeks).
Activity E is on the critical path, so a delay will NOT cause the entire project to be delayed.
The answer cannot be determined.


Step by step
Solved in 1 steps









