QUESTION [25] Manac Ltd manufactures clothing and uses a standard costing system. The following is the standard variable cost for one of their products: Material @ R8.00 per kg Labour @ 1.5 hrs Variable overheads -varying with hours worked: 1.5 hrs @ R6.00 per hour -varying with production Budgeted sales - 11700 units Actual results are as follows: Materials purchased 32 000 kg R262 400 Labour (Rate per hour R16.00) R304 000 R 20.00 22.50 9.00 7.00 Variable overheads -varying with hours worked varying with production Sales Additional information: The budgeted selling price is R50.00 per unit. 1. 12 000 units were manufactured and sold. R108 300 R 78 000 R624 000 2. There were no completed units, work in progress or material on hand at the beginning or end of the period. 1. Material price variance Required: (5) Calculate and state whether the following variances are favourable unfavourable: 1. Material quantity variance 2. Labour rate variance (5) (5) 3. Labour efficiency variance (5) (5) 4. Selling price variance
QUESTION [25] Manac Ltd manufactures clothing and uses a standard costing system. The following is the standard variable cost for one of their products: Material @ R8.00 per kg Labour @ 1.5 hrs Variable overheads -varying with hours worked: 1.5 hrs @ R6.00 per hour -varying with production Budgeted sales - 11700 units Actual results are as follows: Materials purchased 32 000 kg R262 400 Labour (Rate per hour R16.00) R304 000 R 20.00 22.50 9.00 7.00 Variable overheads -varying with hours worked varying with production Sales Additional information: The budgeted selling price is R50.00 per unit. 1. 12 000 units were manufactured and sold. R108 300 R 78 000 R624 000 2. There were no completed units, work in progress or material on hand at the beginning or end of the period. 1. Material price variance Required: (5) Calculate and state whether the following variances are favourable unfavourable: 1. Material quantity variance 2. Labour rate variance (5) (5) 3. Labour efficiency variance (5) (5) 4. Selling price variance
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 5PB: Wrappers Tape makes two products: Simple and Removable. It estimates it will produce 369,991 units...
Related questions
Question
Manac
![QUESTION [25]
Manac Ltd manufactures clothing and uses a standard costing system.
The following is the standard variable cost for one of their products:
Material @ R8.00 per kg
Labour @ 1.5 hrs
Variable overheads
-varying with hours worked: 1.5 hrs @ R6.00 per hour
-varying with production
Budgeted sales - 11700 units
Actual results are as follows:
Materials purchased 32 000 kg
R262 400
Labour (Rate per hour R16.00)
R304 000
R
20.00
22.50
9.00
7.00
Variable overheads
-varying with hours worked
varying with production
Sales
Additional information:
The budgeted selling price is R50.00 per unit.
1. 12 000 units were manufactured and sold.
R108 300
R 78 000
R624 000
2. There were no completed units, work in progress or material on hand at the
beginning or end of the period.
1. Material price variance
Required:
(5)
Calculate and state whether the following variances are favourable
unfavourable:
1. Material quantity variance
2. Labour rate variance
(5)
(5)
3. Labour efficiency variance
(5)
(5)
4. Selling price variance](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ff30aa41e-7ec2-4931-bf06-2e49c68e44dc%2Fbdd34c3f-adc9-40e9-b6ce-9a5a3134ad59%2Fuenb4nq_processed.jpeg&w=3840&q=75)
Transcribed Image Text:QUESTION [25]
Manac Ltd manufactures clothing and uses a standard costing system.
The following is the standard variable cost for one of their products:
Material @ R8.00 per kg
Labour @ 1.5 hrs
Variable overheads
-varying with hours worked: 1.5 hrs @ R6.00 per hour
-varying with production
Budgeted sales - 11700 units
Actual results are as follows:
Materials purchased 32 000 kg
R262 400
Labour (Rate per hour R16.00)
R304 000
R
20.00
22.50
9.00
7.00
Variable overheads
-varying with hours worked
varying with production
Sales
Additional information:
The budgeted selling price is R50.00 per unit.
1. 12 000 units were manufactured and sold.
R108 300
R 78 000
R624 000
2. There were no completed units, work in progress or material on hand at the
beginning or end of the period.
1. Material price variance
Required:
(5)
Calculate and state whether the following variances are favourable
unfavourable:
1. Material quantity variance
2. Labour rate variance
(5)
(5)
3. Labour efficiency variance
(5)
(5)
4. Selling price variance
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College