QUESTION 13 The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a proje Most Probable Immediate Predecessor Activity A B C D E F G H Table 1 Reference: Ref 1 A, B B C D, E F Optimistic Time Time 11 3 15 13 6 3 4 6 2 3 10 5 6 18 4 3 Using Table 1, the earliest start time for activity G is A. 0.0 weeks. B. 10.0 weeks. C. 10.5 weeks. D. 15.5 weeks. E. None of the above Pessimistic Time 14 19 14 7 11 13 6 9
QUESTION 13 The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a proje Most Probable Immediate Predecessor Activity A B C D E F G H Table 1 Reference: Ref 1 A, B B C D, E F Optimistic Time Time 11 3 15 13 6 3 4 6 2 3 10 5 6 18 4 3 Using Table 1, the earliest start time for activity G is A. 0.0 weeks. B. 10.0 weeks. C. 10.5 weeks. D. 15.5 weeks. E. None of the above Pessimistic Time 14 19 14 7 11 13 6 9
Related questions
Question

Transcribed Image Text:QUESTION 13
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project
Immediate
Most Probable
Predecessor
Activity
A
B
C
D
E
F
G
H
Table 1
Reference: Ref 1
A, B
B
C
D, E
F
Optimistic Time Time
11
13
5
13
6
3
4
6
2
3
10
5
6
8
4
13
Using Table 1, the earliest start time for activity G is
OA. 0.0 weeks.
OB. 10.0 weeks.
O C. 10.5 weeks.
O D. 15.5 weeks.
O E. None of the above
Pessimistic Time
14
19
14
7
11
13
6
9
decessors are p