Question 1- Week 31 Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1 ($68,000) and Job L2 ($30 000). The following information is available: i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours, respectively. ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March). Direct materials used, direct labour incurred and machine hours consumed were as shown in the following table: Job numbers Direct material Direct labour Machine hours L1 $15,000 $30,000 900 L2 33,000 1,600 L3 45,000 65,000 2,000 ii) Manufacturing overhead incurred during the first quarter was $215,000. iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing a profit of $30,000 for the company. Required: a) Calculate the company's predetermined overhead rate. b) Calculate manufacturing overhead applied to production for the first quarter. c) Determine the cost of jobs completed in the first quarter. d) Determine the cost of the jobs still in process at the end of the first quarter.
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
![Question 1- Week 31
Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1
($68,000) and Job L2 ($30 000). The following information is available:
i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead
and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours,
respectively.
ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March).
Direct materials used, direct labour incurred and machine hours consumed were as shown in the
following table:
Job numbers
Direct material
Direct labour
Machine hours
L1
$15,000
$30,000
900
L2
33,000
1,600
L3
45,000
65,000
2,000
ii) Manufacturing overhead incurred during the first quarter was $215,000.
iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing
a profit of $30,000 for the company.
Required:
a) Calculate the company's predetermined overhead rate.
b) Calculate manufacturing overhead applied to production for the first quarter.
c) Determine the cost of jobs completed in the first quarter.
d) Determine the cost of the jobs still in process at the end of the first quarter.
SHOW YOUR WORKING](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F7cad30b3-9853-4467-95fe-69cc5a147f66%2Fb2648da2-3f2b-40be-bcfd-67e867cd2a95%2Fhl2c8sd_processed.jpeg&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Foundations of Business (MindTap Course List)](https://www.bartleby.com/isbn_cover_images/9781337386920/9781337386920_smallCoverImage.gif)
![Foundations of Business - Standalone book (MindTa…](https://www.bartleby.com/isbn_cover_images/9781285193946/9781285193946_smallCoverImage.gif)