Question 1- Week 31 Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1 ($68,000) and Job L2 ($30 000). The following information is available: i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours, respectively. ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March). Direct materials used, direct labour incurred and machine hours consumed were as shown in the following table: Job numbers Direct material Direct labour Machine hours L1 $15,000 $30,000 900 L2 33,000 1,600 L3 45,000 65,000 2,000 ii) Manufacturing overhead incurred during the first quarter was $215,000. iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing a profit of $30,000 for the company. Required: a) Calculate the company's predetermined overhead rate. b) Calculate manufacturing overhead applied to production for the first quarter. c) Determine the cost of jobs completed in the first quarter. d) Determine the cost of the jobs still in process at the end of the first quarter.

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.1SD: Scenario 4 Sharon Gillespie, a new buyer at Visionex, Inc., was reviewing quotations for a tooling...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Question 1- Week 31
Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1
($68,000) and Job L2 ($30 000). The following information is available:
i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead
and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours,
respectively.
ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March).
Direct materials used, direct labour incurred and machine hours consumed were as shown in the
following table:
Job numbers
Direct material
Direct labour
Machine hours
L1
$15,000
$30,000
900
L2
33,000
1,600
L3
45,000
65,000
2,000
ii) Manufacturing overhead incurred during the first quarter was $215,000.
iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing
a profit of $30,000 for the company.
Required:
a) Calculate the company's predetermined overhead rate.
b) Calculate manufacturing overhead applied to production for the first quarter.
c) Determine the cost of jobs completed in the first quarter.
d) Determine the cost of the jobs still in process at the end of the first quarter.
SHOW YOUR WORKING
Transcribed Image Text:Question 1- Week 31 Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1 ($68,000) and Job L2 ($30 000). The following information is available: i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours, respectively. ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March). Direct materials used, direct labour incurred and machine hours consumed were as shown in the following table: Job numbers Direct material Direct labour Machine hours L1 $15,000 $30,000 900 L2 33,000 1,600 L3 45,000 65,000 2,000 ii) Manufacturing overhead incurred during the first quarter was $215,000. iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing a profit of $30,000 for the company. Required: a) Calculate the company's predetermined overhead rate. b) Calculate manufacturing overhead applied to production for the first quarter. c) Determine the cost of jobs completed in the first quarter. d) Determine the cost of the jobs still in process at the end of the first quarter. SHOW YOUR WORKING
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Foundations of Business (MindTap Course List)
Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Foundations of Business - Standalone book (MindTa…
Foundations of Business - Standalone book (MindTa…
Marketing
ISBN:
9781285193946
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College