Q5. As a civil engineer, you have been assign to prepare earthwork cost estimation for a proposed road alignment projects between Pekan Nenas and Pontian Kecil. Table Q5 shows the list of volume cut and fill for each cross-section between CH 4000m to CH 5700m at 50 m intervals. Table Q5 Chainage (m) Volume Cut (m³) Volume Fill (m³) 4000 6000 2000 4050 2800 2103 4100 2999 2010 4150 2846 2105 4200 2501 2090 4250 2090 2149 4300 2000 2515 4350 2000 2905 4400 2000 3110 4450 2000 2989 4500 2000 2650 4550 2000 2199 4600 2309 2199 4650 2650 2000 4700 3300 2000 The following information are required in preparing earthwork cost estimation claim to the client as soon as possible: progress Plot a mass-haul diagram between the chainage 4000m to 4700m using the volumes obtained in Table Q5. Use a scale of 1cm = 50 m for the x-axis and 2 cm 500 m3 for the y-axis. (a) (b) Estimate the haulage costs between the chainage 4000m to 4450m. Proposed balancing line and free haul distance are at +4000m3 and 200m respectively. The transportation charges are:- : RM 1.50 / m3 : RM 0.80 / stn. M. Free-haul Over-haul Assuming that the balancing line of +3500 m3 is to be applied to the mass-hall diagram calculations, explain how this would affect the cost estimation.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Q5. As a civil engineer, you have been assign to prepare earthwork cost estimation for a
proposed road alignment projects between Pekan Nenas and Pontian Kecil. Table Q5
shows the list of volume cut and fill for each cross-section between CH 4000m to CH
5700m at 50 m intervals.
Table Q5
Chainage (m)
Volume Cut (m³)
Volume Fill (m³)
4000
6000
2000
4050
2800
2103
4100
2999
2010
4150
2846
2105
4200
2501
2090
4250
2090
2149
4300
2000
2515
4350
2000
2905
4400
2000
3110
4450
2000
2989
4500
2000
2650
4550
2000
2199
4600
2309
2199
4650
2650
2000
4700
3300
2000
The following information are required in preparing earthwork cost estimation progress
claim to the client as soon as possible:
(a)
Plot a mass-haul diagram between the chainage 4000m to 4700m using the volumes
obtained in Table Q5. Use a scale of 1cm = 50 m for the x-axis and 2 cm = 500 m3
for the y-axis.
(b) Estimate the haulage costs between the chainage 4000m to 4450m. Proposed
balancing line and free haul distance are at +4000m3 and 200m respectively. The
transportation charges are:-
: RM 1.50 / m3
: RM 0.80 / stn. M.
Free-haul
Over-haul
Assuming that the balancing line of +3500 m3 is to be applied to the mass-hall diagram
calculations, explain how this would affect the cost estimation.
Transcribed Image Text:Q5. As a civil engineer, you have been assign to prepare earthwork cost estimation for a proposed road alignment projects between Pekan Nenas and Pontian Kecil. Table Q5 shows the list of volume cut and fill for each cross-section between CH 4000m to CH 5700m at 50 m intervals. Table Q5 Chainage (m) Volume Cut (m³) Volume Fill (m³) 4000 6000 2000 4050 2800 2103 4100 2999 2010 4150 2846 2105 4200 2501 2090 4250 2090 2149 4300 2000 2515 4350 2000 2905 4400 2000 3110 4450 2000 2989 4500 2000 2650 4550 2000 2199 4600 2309 2199 4650 2650 2000 4700 3300 2000 The following information are required in preparing earthwork cost estimation progress claim to the client as soon as possible: (a) Plot a mass-haul diagram between the chainage 4000m to 4700m using the volumes obtained in Table Q5. Use a scale of 1cm = 50 m for the x-axis and 2 cm = 500 m3 for the y-axis. (b) Estimate the haulage costs between the chainage 4000m to 4450m. Proposed balancing line and free haul distance are at +4000m3 and 200m respectively. The transportation charges are:- : RM 1.50 / m3 : RM 0.80 / stn. M. Free-haul Over-haul Assuming that the balancing line of +3500 m3 is to be applied to the mass-hall diagram calculations, explain how this would affect the cost estimation.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Measuring sitework, excavation and piling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning