Q3. The accountant for Barry Ltd compares each month's actual results with a monthly plan. The standard direct labour rates and the standard hours allowed, given the actual output in April, are shown in the following schedule: Standard direct labour rate Standard direct labour hours allowed, given April output Labour class III Labour class II Labour class I per hour $26.00 $22.00 $12.00 1 000 1 000 1 000 A new union contract negotiated in March resulted in actual wage rates that differed from the standard rates. The actual direct labour hours worked and the actual direct labour rates per hour for April were as follows. Actual direct labour rate per hour $28.00 Actual direct labour hours Labour class III 1 100 Labour class II $23.00 1 300 Labour class I $14.00 750 Required: 1. Calculate the following variances for April, indicating whether each is favourable or unfavourable: (a) direct labour rate variance for each labour class. (b) direct labour efficiency variance for each labour class. 2. Discuss two advantages and two disadvantages of a standard costing system in which the standard direct labour rates per hour are not changed during the year to reflect events such as a new labour contract.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Topic Video
Question

1. Calculate the following variances for April, indicating whether each is favourable or
unfavourable:
(a) direct labour rate variance for each labour class.
(b) direct labour efficiency variance for each labour class.
2. Discuss two advantages and two disadvantages of a standard costing system in which the
standard direct labour rates per hour are not changed during the year to reflect events such
as a new labour contract

Q3. The accountant for Barry Ltd compares each month's actual results with a monthly plan.
The standard direct labour rates and the standard hours allowed, given the actual output in
April, are shown in the following schedule:
Standard direct labour
rate
Standard direct labour
hours allowed,
given April output
Labour class III
Labour class II
Labour class I
per hour
$26.00
$22.00
$12.00
1 000
1 000
1 000
A new union contract negotiated in March resulted in actual wage rates that differed from the
standard rates. The actual direct labour hours worked and the actual direct labour rates per
hour for April were as follows.
Actual direct labour rate
per hour
$28.00
Actual direct labour hours
Labour class III
1 100
Labour class II
$23.00
1 300
Labour class I
$14.00
750
Required:
1. Calculate the following variances for April, indicating whether each is favourable or
unfavourable:
(a) direct labour rate variance for each labour class.
(b) direct labour efficiency variance for each labour class.
2. Discuss two advantages and two disadvantages of a standard costing system in which the
standard direct labour rates per hour are not changed during the year to reflect events such
as a new labour contract.
Transcribed Image Text:Q3. The accountant for Barry Ltd compares each month's actual results with a monthly plan. The standard direct labour rates and the standard hours allowed, given the actual output in April, are shown in the following schedule: Standard direct labour rate Standard direct labour hours allowed, given April output Labour class III Labour class II Labour class I per hour $26.00 $22.00 $12.00 1 000 1 000 1 000 A new union contract negotiated in March resulted in actual wage rates that differed from the standard rates. The actual direct labour hours worked and the actual direct labour rates per hour for April were as follows. Actual direct labour rate per hour $28.00 Actual direct labour hours Labour class III 1 100 Labour class II $23.00 1 300 Labour class I $14.00 750 Required: 1. Calculate the following variances for April, indicating whether each is favourable or unfavourable: (a) direct labour rate variance for each labour class. (b) direct labour efficiency variance for each labour class. 2. Discuss two advantages and two disadvantages of a standard costing system in which the standard direct labour rates per hour are not changed during the year to reflect events such as a new labour contract.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education