PT ABC produces disinfectants by mixing 2 chemical solutions for mixingin a machine to become a disinfectant solution (solution 1 and solution 2). Solution 1 isthe first process which was carried out on workstation A for 0.5 minutes per solution latercontinued at workstation B for 0.2 minutes per solution. Which then istogether solution 1 was mixed with solution 2 on workstation C for 0.8 minutes persolution. Workstations B and C are processed at workstation D for the mixing processtogether where the process is for 6 minutes per solution until it becomes a solutiondisinfectant to sell to customers.a. Which workstations are the bottleneck? Explain with a picture of the workstation.b. What is the resulting time (throughput time) of the entire work system above?c. How much disinfectant solution can a company produce per hour?
Oh no! Our experts couldn't answer your question.
Don't worry! We won't leave you hanging. Plus, we're giving you back one question for the inconvenience.
PT ABC produces disinfectants by mixing 2 chemical solutions for mixing
in a machine to become a disinfectant solution (solution 1 and solution 2). Solution 1 is
the first process which was carried out on workstation A for 0.5 minutes per solution later
continued at workstation B for 0.2 minutes per solution. Which then is
together solution 1 was mixed with solution 2 on workstation C for 0.8 minutes per
solution. Workstations B and C are processed at workstation D for the mixing process
together where the process is for 6 minutes per solution until it becomes a solution
disinfectant to sell to customers.
a. Which workstations are the bottleneck? Explain with a picture of the workstation.
b. What is the resulting time (throughput time) of the entire work system above?
c. How much disinfectant solution can a company produce per hour?