Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: A 3 1 BUO C D EFGI H I J K L M N3W|WN|HWA34W 1 2 2 2 A B BC BF D H II H EGIJ GIJ KL

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question

Can you draw the network diagram, im confused on the BC into F? 

**Project Activities and Precedence Relations**

The table below identifies various activities involved in a project, their respective durations, and their precedence relationships. Each activity is represented by a letter, has a specific duration (in arbitrary time units), and may depend on the completion of other activities.

| **Activity** | **Duration** | **Preceded By** |
|--------------|--------------|-----------------|
| A            | 3            | -               |
| B            | 1            | A               |
| C            | 3            | A               |
| D            | 4            | B               |
| E            | 4            | B               |
| F            | 4            | B, C            |
| G            | 3            | B, F            |
| H            | 1            | D               |
| I            | 2            | H               |
| J            | 3            | H               |
| K            | 3            | E, G, I, J      |
| L            | 2            | G, I, J         |
| M            | 2            | K, L            |

**Explanation and Analysis:**

- **Activity A** is the starting point with no preceding activities.
- **Activities B and C** can only start once Activity A is completed.
- **Activity D** depends on the completion of Activity B.
- **Activity E** requires the completion of Activity B as well.
- **Activity F** can only begin once both Activities B and C are finished.
- **Activity G** follows once Activities B and F are completed.
- **Activity H** is contingent upon the completion of Activity D.
- **Activities I and J** require the completion of Activity H before they can start.
- **Activity K** can commence once Activities E, G, I, and J are completed.
- **Activity L** needs the completion of Activities G, I, and J.
- **Activity M** can only start after Activities K and L are finished.

This sequence of activities and dependencies is crucial for effective project management and scheduling, ensuring all tasks are completed in a timely and efficient manner.
Transcribed Image Text:**Project Activities and Precedence Relations** The table below identifies various activities involved in a project, their respective durations, and their precedence relationships. Each activity is represented by a letter, has a specific duration (in arbitrary time units), and may depend on the completion of other activities. | **Activity** | **Duration** | **Preceded By** | |--------------|--------------|-----------------| | A | 3 | - | | B | 1 | A | | C | 3 | A | | D | 4 | B | | E | 4 | B | | F | 4 | B, C | | G | 3 | B, F | | H | 1 | D | | I | 2 | H | | J | 3 | H | | K | 3 | E, G, I, J | | L | 2 | G, I, J | | M | 2 | K, L | **Explanation and Analysis:** - **Activity A** is the starting point with no preceding activities. - **Activities B and C** can only start once Activity A is completed. - **Activity D** depends on the completion of Activity B. - **Activity E** requires the completion of Activity B as well. - **Activity F** can only begin once both Activities B and C are finished. - **Activity G** follows once Activities B and F are completed. - **Activity H** is contingent upon the completion of Activity D. - **Activities I and J** require the completion of Activity H before they can start. - **Activity K** can commence once Activities E, G, I, and J are completed. - **Activity L** needs the completion of Activities G, I, and J. - **Activity M** can only start after Activities K and L are finished. This sequence of activities and dependencies is crucial for effective project management and scheduling, ensuring all tasks are completed in a timely and efficient manner.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

What would be the critical path and the project duration for M?

Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Power Plant Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY