Processing Time (seconds) Station Tasks A 1. Heat-stake lens to bezel 14 Preparation 2. Inspect bezel 26 3. Clean switch holes 10 4. Install set switch in bezel 18 Total time for A 68 в 5. Check switch travel 23 6. Clean inside bezel 7. Install module in bezel Preparation 2 12 25 Total time for B 60 8. Install battery clip on module 20 Battery installation . Heat-stake battery clip on module 20 10. Install two batteries in module 22 11. Check switch 8 Total time for C 70 D 12. Install band 45 Band installation 13. Inspect band 13 Total time for D 58 E 14. Cosmetic inspection 4 Packaging preparation 15. Final test 71 Total time for E 75 F 16. Place watch and cuff in display box 20 Watch packaging 17. Place cover in display box base 14 18. Place owner's manual and box into tub 30 Total time for F 64 ..... ....
The Geneva Watch Corporation manufactures watches on a conveyor belt with six stations. One worker stands at each station and performs the following tasks:Workers get paid $10 per hour. You can ignore any idle time of workers resulting from
the beginning or the end of the day.
a. What is the labor content?
b. Assume a
c. Assume a demand rate of 50 watches per hour. What is the target manpower?
d. An external supplier suggests shipping the battery module with preinstalled batteries,
thereby eliminating the need for step 10. How would that impact process capacity?
e. How could you increase the capacity of the process by rebalancing it?
Trending now
This is a popular solution!
Step by step
Solved in 3 steps