Problem 18: Predetermined Factory Overhead believes that the company would be better if it will use two factory overhead single factory overhead rate that is based on machine hours. Its manager Davao Corp. uses job order costing system to produce its products. It uses a rates, one based on material costs and the other one is based machine hours. The following data are for year 2020: Materials related Factory overhead Machine related Factory overhead Total Budgeted Factory overhead Costs of materials used on jobs Total Machine hours Data related to three jobs worked on in December follow: Material Costs Direct Labor Costs Machine Hours used Job # 1 168,000 128,000 68,000 Budgeted FOH 3,840,000 10,400,000 14,240,000 Job # 2 656,000 104,000 36,000 Job Order Costing 12,800,000 1,600,000 Job # 3 312,000 144,000 23,200 Actual factory overhead related to materials was P318,400 and actual factory overhead related to machine hours was P846,400. Required: 1. Determine the predetermine factory overhead rate based on machine hours, assuming Davao Corp. uses only machine hours to compute the factory overhead applied. 2. Determine the factory overhead applied and total costs of each job. 3. Using two factory overhead rates as suggested by the manager, recomputed requirements 1 and 2.

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter5: Product And Service Costing: Job-order System
Section: Chapter Questions
Problem 27P: Firenza Company manufactures specialty tools to customer order. Budgeted overhead for the coming...
icon
Related questions
Topic Video
Question
Problem 18: Predetermined Factory Overhead
believes that the company would be better if it will use two factory overhead
single factory overhead rate that is based on machine hours. Its manager
Davao Corp. uses job order costing system to produce its products. It uses a
rates, one based on material costs and the other one is based machine hours.
The following data are for year 2020:
Materials related Factory overhead
Machine related Factory overhead
Total Budgeted Factory overhead
Costs of materials used on jobs
Total Machine hours
Data related to three jobs worked on in December follow:
Material Costs
Direct Labor Costs
Machine Hours used
Job # 1
168,000
128,000
68,000
Budgeted FOH
3,840,000
10,400,000
14,240,000
Job # 2
656,000
104,000
36,000
Job Order Costing
12,800,000
1,600,000
Job # 3
312,000
144,000
23,200
Actual factory overhead related to materials was P318,400 and actual factory
overhead related to machine hours was P846,400.
Required:
1. Determine the predetermine factory overhead rate based on machine hours,
assuming Davao Corp. uses only machine hours to compute the factory
overhead applied.
2. Determine the factory overhead applied and total costs of each job.
3. Using two factory overhead rates as suggested by the manager, recomputed
requirements 1 and 2.
Transcribed Image Text:Problem 18: Predetermined Factory Overhead believes that the company would be better if it will use two factory overhead single factory overhead rate that is based on machine hours. Its manager Davao Corp. uses job order costing system to produce its products. It uses a rates, one based on material costs and the other one is based machine hours. The following data are for year 2020: Materials related Factory overhead Machine related Factory overhead Total Budgeted Factory overhead Costs of materials used on jobs Total Machine hours Data related to three jobs worked on in December follow: Material Costs Direct Labor Costs Machine Hours used Job # 1 168,000 128,000 68,000 Budgeted FOH 3,840,000 10,400,000 14,240,000 Job # 2 656,000 104,000 36,000 Job Order Costing 12,800,000 1,600,000 Job # 3 312,000 144,000 23,200 Actual factory overhead related to materials was P318,400 and actual factory overhead related to machine hours was P846,400. Required: 1. Determine the predetermine factory overhead rate based on machine hours, assuming Davao Corp. uses only machine hours to compute the factory overhead applied. 2. Determine the factory overhead applied and total costs of each job. 3. Using two factory overhead rates as suggested by the manager, recomputed requirements 1 and 2.
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
College Accounting, Chapters 1-27
College Accounting, Chapters 1-27
Accounting
ISBN:
9781337794756
Author:
HEINTZ, James A.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College