Problem 1. For a software project using semi-detached mode of 30000 lines of code estimate effort, time of development, and average staffing for the project. Problem 2. Consider a project having 30000 lines of code which is an embedded software and critical area application with high reliability. Estimate effort, time of development, and average staffing for the project. Problem 3. A management information system (MIS) from an organization having offices of several places across the country (1) Database part-smi detached with 80000 lines of code with high application experience developers  (2) Graphical User Interface- organic with 20000 lines of code with high programming language personnel (3) Communication part -embedded with 300000 lines of code  Estimate effort, time of development, and average staffing for the project. Problem 4. Make a rough estimation of person month, time development for your research project using COCOMO model.

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question

Problem 1. For a software project using semi-detached mode of 30000 lines of code estimate effort, time of development, and average staffing for the project.

Problem 2. Consider a project having 30000 lines of code which is an embedded software and critical area application with high reliability. Estimate effort, time of development, and average staffing for the project.

Problem 3. A management information system (MIS) from an organization having offices of several places across the country

(1) Database part-smi detached with 80000 lines of code with high application experience developers 

(2) Graphical User Interface- organic with 20000 lines of code with high programming language personnel

(3) Communication part -embedded with 300000 lines of code 

Estimate effort, time of development, and average staffing for the project.

Problem 4. Make a rough estimation of person month, time development for your research project using COCOMO model. 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Software Development Approaches
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education