Problem 1. For a software project using semi-detached mode of 30000 lines of code estimate effort, time of development, and average staffing for the project. Problem 2. Consider a project having 30000 lines of code which is an embedded software and critical area application with high reliability. Estimate effort, time of development, and average staffing for the project. Problem 3. A management information system (MIS) from an organization having offices of several places across the country (1) Database part-smi detached with 80000 lines of code with high application experience developers (2) Graphical User Interface- organic with 20000 lines of code with high programming language personnel (3) Communication part -embedded with 300000 lines of code Estimate effort, time of development, and average staffing for the project. Problem 4. Make a rough estimation of person month, time development for your research project using COCOMO model.
Problem 1. For a software project using semi-detached mode of 30000 lines of code estimate effort, time of development, and average staffing for the project.
Problem 2. Consider a project having 30000 lines of code which is an embedded software and critical area application with high reliability. Estimate effort, time of development, and average staffing for the project.
Problem 3. A management
(1)
(2) Graphical User Interface- organic with 20000 lines of code with high programming language personnel
(3) Communication part -embedded with 300000 lines of code
Estimate effort, time of development, and average staffing for the project.
Problem 4. Make a rough estimation of person month, time development for your research project using COCOMO model.