Problem 1 An advice on the size of the solid waste collection truck is to be provided. The compactor trucks available from a local supplier are rated to achieve a density (DT) of 400 kg/m³ (compacted with maximum truck size of 4 m³) with initial cost of $100,000 and interest rate of 10.25 %. The truck is estimated to have an average operating and maintenance cost of $5.50/km over the five-year life of the truck. The unloading time is 10.0 minutes. The average route length is 7 km while the disposal site is 9.6 km away from the collection route. The average haul speed is 5-30 km/h. From experience, a delay time of 15 minutes can be expected per the trip. The uncompacted density of the solid waste is 100 kg/m³. Each stop typically contains a total 12 kgs of waste. Assume: The time for each pickup (tp) is 0.025 hrs. Two trips per day will be made to the disposal site. • The crew will include two operators with an average hourly wage rate of $15.00 per hour. • The overhead rate is 125 % of the hourly wage rate. Five working days per week with 9 working hours per day Two 15-minute breaks per day are taken by the truck operator. Determine: 1. The solid waste that can be carried by the truck (VT) in m³ 2. The number of stops that can be handled by the truck (NP) 3. Average truck cost ($/Mg) 4. Average Labour cost ($/Mg) 5. The total annual cost is (Truck + Labour costs) 6. Annual cost per service stop ($) 7. Weekly cost per service stop ($)

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Problem 1
An advice on the size of the solid waste collection truck is to be provided. The compactor trucks available
from a local supplier are rated to achieve a density (DT) of 400 kg/m³ (compacted with maximum truck size
of 4 m³) with initial cost of $100,000 and interest rate of 10.25 %. The truck is estimated to have an
average operating and maintenance cost of $5.50/km over the five-year life of the truck.
The unloading time is 10.0 minutes. The average route length is 7 km while the disposal site is 9.6 km away
from the collection route. The average haul speed is 5-30 km/h. From experience, a delay time of 15
minutes can be expected per the trip. The uncompacted density of the solid waste is 100 kg/m³. Each stop
typically contains a total 12 kgs of waste.
Assume:
The time for each pickup (tp) is 0.025 hrs.
Two trips per day will be made to the disposal site.
• The crew will include two operators with an average hourly wage rate of $15.00 per hour.
• The overhead rate is 125 % of the hourly wage rate.
Five working days per week with 9 working hours per day
Two 15-minute breaks per day are taken by the truck operator.
Determine:
1. The solid waste that can be carried by the truck (VT) in m³
2. The number of stops that can be handled by the truck (NP)
3. Average truck cost ($/Mg)
4. Average Labour cost ($/Mg)
5. The total annual cost is (Truck + Labour costs)
6. Annual cost per service stop ($)
7. Weekly cost per service stop ($)
Transcribed Image Text:Problem 1 An advice on the size of the solid waste collection truck is to be provided. The compactor trucks available from a local supplier are rated to achieve a density (DT) of 400 kg/m³ (compacted with maximum truck size of 4 m³) with initial cost of $100,000 and interest rate of 10.25 %. The truck is estimated to have an average operating and maintenance cost of $5.50/km over the five-year life of the truck. The unloading time is 10.0 minutes. The average route length is 7 km while the disposal site is 9.6 km away from the collection route. The average haul speed is 5-30 km/h. From experience, a delay time of 15 minutes can be expected per the trip. The uncompacted density of the solid waste is 100 kg/m³. Each stop typically contains a total 12 kgs of waste. Assume: The time for each pickup (tp) is 0.025 hrs. Two trips per day will be made to the disposal site. • The crew will include two operators with an average hourly wage rate of $15.00 per hour. • The overhead rate is 125 % of the hourly wage rate. Five working days per week with 9 working hours per day Two 15-minute breaks per day are taken by the truck operator. Determine: 1. The solid waste that can be carried by the truck (VT) in m³ 2. The number of stops that can be handled by the truck (NP) 3. Average truck cost ($/Mg) 4. Average Labour cost ($/Mg) 5. The total annual cost is (Truck + Labour costs) 6. Annual cost per service stop ($) 7. Weekly cost per service stop ($)
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning