Preston Concrete is a major supplier of concrete to residential and commercial builders in the Pacific Northwest. The. company's general pricng poliy s to et prices at $126 per cubic yard. Delverie for 2020 were 390,000 cubic yards, and tota costs were: Material costs | 527,144,000 Yera operation 55,460,000 costs Administrative 51,560,000 $4,149,600 of the estimated total yard operation costs were Variable, and al of the administrative costs were fixed. In addition'to the costs above, estimated fxed defivery costs were $220,000 for the year, and estimated variable delvery costs were $8.50 per mile and $42.50 per truck hour. The. ate per mile refect the fact that more mils resultin more 925, 0i, and maintenance. The rate per truck hour reflects the fact tha trucks that are waiting at a obsite are kept Funing (5o the concrete mix won't s0idify), and drivers continue to get paid during that time. Near the end of 2020, Fairview Construction Company asked for a delivery of 5,300 cubic yards of concrete but was unwiling to pay the reguiar prie; 1t was only willng to pay. 477 per cubic yard. Preston estimated that the job would require 7,000 miles o driving and 220 truck hours. The housing market in the Pacific Northwest had siowsd during recent months, eaving Preston with enough capacity to fil the order; but s sales manager was reuctant to commit to such a reduced price. REQUIRED 1 Preston accepted the offer, what would the profitor loss be (enter a loss s 2 negative number)?
Preston Concrete is a major supplier of concrete to residential and commercial builders in the Pacific Northwest. The. company's general pricng poliy s to et prices at $126 per cubic yard. Delverie for 2020 were 390,000 cubic yards, and tota costs were: Material costs | 527,144,000 Yera operation 55,460,000 costs Administrative 51,560,000 $4,149,600 of the estimated total yard operation costs were Variable, and al of the administrative costs were fixed. In addition'to the costs above, estimated fxed defivery costs were $220,000 for the year, and estimated variable delvery costs were $8.50 per mile and $42.50 per truck hour. The. ate per mile refect the fact that more mils resultin more 925, 0i, and maintenance. The rate per truck hour reflects the fact tha trucks that are waiting at a obsite are kept Funing (5o the concrete mix won't s0idify), and drivers continue to get paid during that time. Near the end of 2020, Fairview Construction Company asked for a delivery of 5,300 cubic yards of concrete but was unwiling to pay the reguiar prie; 1t was only willng to pay. 477 per cubic yard. Preston estimated that the job would require 7,000 miles o driving and 220 truck hours. The housing market in the Pacific Northwest had siowsd during recent months, eaving Preston with enough capacity to fil the order; but s sales manager was reuctant to commit to such a reduced price. REQUIRED 1 Preston accepted the offer, what would the profitor loss be (enter a loss s 2 negative number)?
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
Preston Concrete is a major supplier of concrete to residential and commercial builders in the Pacific Northwest. The. company's general pricng poliy s to et prices at $126 per cubic yard. Delverie for 2020 were 390,000 cubic yards, and tota costs were: Material costs | 527,144,000 Yera operation 55,460,000 costs Administrative 51,560,000 $4,149,600 of the estimated total yard operation costs were Variable, and al of the administrative costs were fixed. In addition'to the costs above, estimated fxed defivery costs were $220,000 for the year, and estimated variable delvery costs were $8.50 per mile and $42.50 per truck hour. The. ate per mile refect the fact that more mils resultin more 925, 0i, and maintenance. The rate per truck hour reflects the fact tha trucks that are waiting at a obsite are kept Funing (5o the concrete mix won't s0idify), and drivers continue to get paid during that time. Near the end of 2020, Fairview Construction Company asked for a delivery of 5,300 cubic yards of concrete but was unwiling to pay the reguiar prie; 1t was only willng to pay. 477 per cubic yard. Preston estimated that the job would require 7,000 miles o driving and 220 truck hours. The housing market in the Pacific Northwest had siowsd during recent months, eaving Preston with enough capacity to fil the order; but s sales manager was reuctant to commit to such a reduced price. REQUIRED 1 Preston accepted the offer, what would the profitor loss be (enter a loss s 2 negative number)?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education