Prepare the rough estimate for a proposed commercial compels for a municipal corporation for the following data. o Plinth Area = 500m2/floor o Height of each story 3.5m o No. of stores = G+2 o Cubical content rate = $100/m %3D Provided for a following as a percentage of structured cost • water supply & Sanitary arrangement 8% • Electrification 6% Fluctuation of rates 5% Contractors profit 10% Petty supervision & contingencies 3%
Prepare the rough estimate for a proposed commercial compels for a municipal corporation for the following data. o Plinth Area = 500m2/floor o Height of each story 3.5m o No. of stores = G+2 o Cubical content rate = $100/m %3D Provided for a following as a percentage of structured cost • water supply & Sanitary arrangement 8% • Electrification 6% Fluctuation of rates 5% Contractors profit 10% Petty supervision & contingencies 3%
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter16: Budget Estimating
Section: Chapter Questions
Problem 4RQ: Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a...
Related questions
Question
![Prepare the rough estimate for a proposed commercial compels for a municipal
corporation for the following data.
o Plinth Area = 500m2/floor
o Height of each story = 3.5m
o No. of stores = G+2
o Cubical content rate = $100/m³
Provided for a following as a percentage of structured cost
• water supply & Sanitary arrangement 8%
Electrification 6%
Fluctuation of rates 5%
Contractors profit 10%
Petty supervision & contingencies 3%
SAAD RIDHAGEPU. EDU.IO
39](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fa87b34a7-89f4-42d9-8578-cb328a209448%2Fa37a5c15-38a8-4338-975e-c8be99f326e7%2Fuub71h_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Prepare the rough estimate for a proposed commercial compels for a municipal
corporation for the following data.
o Plinth Area = 500m2/floor
o Height of each story = 3.5m
o No. of stores = G+2
o Cubical content rate = $100/m³
Provided for a following as a percentage of structured cost
• water supply & Sanitary arrangement 8%
Electrification 6%
Fluctuation of rates 5%
Contractors profit 10%
Petty supervision & contingencies 3%
SAAD RIDHAGEPU. EDU.IO
39
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
![Solid Waste Engineering](https://www.bartleby.com/isbn_cover_images/9781305635203/9781305635203_smallCoverImage.gif)
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
![Solid Waste Engineering](https://www.bartleby.com/isbn_cover_images/9781305635203/9781305635203_smallCoverImage.gif)
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,