Prakesh Company has the following data for one of its manufacturing cells: Maximum units produced in a month: 62,500 units Actual units produced in a month: 56,250 units Hours of production labor in one month: 10,000 hours Required: 1. Compute the theoretical cycle time. Round
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Prakesh Company has the following data for one of its manufacturing cells:
Maximum units produced in a month: 62,500 units |
Actual units produced in a month: 56,250 units |
Hours of production labor in one month: 10,000 hours |
Required:
1. Compute the theoretical cycle time. Round your answer to the nearest whole minute.
fill in the blank 1 minutes per unit
2. Compute the actual cycle time. Round your answer to the nearest whole minute.
fill in the blank 2 minutes per unit
3. Compute the theoretical velocity. Round your answer to the nearest whole unit.
fill in the blank 3 units per hour
4. Compute the actual velocity. Round your answer to the nearest whole unit.
fill in the blank 4 units per hour