PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities: Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 3 $1,000 $3,300 В 2 1 $2,160 $2,460 3 2 $1,300 $3,000 D 7 3 $2,000 $2,500 A 3 $1,650 $2,100 B F 4 3 $4,100 $5,260 G 4 2 $1,650 $2,100 D, E What is the overall duration of the project? Number Which of the following activities has the lowest crash cost per week? O A O D O E
PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities: Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 3 $1,000 $3,300 В 2 1 $2,160 $2,460 3 2 $1,300 $3,000 D 7 3 $2,000 $2,500 A 3 $1,650 $2,100 B F 4 3 $4,100 $5,260 G 4 2 $1,650 $2,100 D, E What is the overall duration of the project? Number Which of the following activities has the lowest crash cost per week? O A O D O E
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:Which of the following activities has the highest crash cost per week?
G
F
В
If you wanted to shorten the overall duration of the project, which activity should you crash first?
C
A
E
What is the total cost of crashing the project from its current duration down to 11 weeks?
Number
What is the total cost of crashing the project from its original duration to 9 weeks?
Number

Transcribed Image Text:PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After
gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:
Activity
Normal Time (weeks)
Crashed Time (weeks)
Normal Cost
Crashed Cost
Predecessor(s)
А
3
$1,000
$3,300
В
1
$2,160
$2,460
3
2
$1,300
$3,000
D
7
3
$2,000
$2,500
A
E
3
$1,650
$2,100
B
F
4
3
$4,100
$5,260
G
4
2
$1,650
$2,100
D, E
What is the overall duration of the project?
Number
Which of the following activities has the lowest crash cost per week?
O A
O E
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 4 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.