PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed. Activity Normal Time (weeks) Crashed Time (weeks)| Normal Cost Crashed Cost Predecessor(s) A 5 $900 $1,300 B 3 $400 $500 6 5 $500 $675 3 $900 $1,200 A E 6 3 $1,500 $2,400 F $600 $700 What is the duration of the project (in weeks)? Number What is the target duration of the project (after crashing the project)? Number By how many weeks should activity A be crashed? Number By how many weeks should activity B be crashed? Number By how many weeks should activity C be crashed? Number

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he
wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.
Activity
Normal Time (weeks)
Crashed Time (weeks) Normal Cost
Crashed Cost
Predecessor(s)
A
5
$900
$1,300
В
3
$400
$500
5
$500
$675
D
3
$900
$1,200
A
E
3
$1,500
$2,400
C
F
3
2
$600
$700
В
What is the duration of the project (in weeks)?
Number
What is the target duration of the project (after crashing the project)?
Number
By how many weeks should activity A be crashed?
Number
By how many weeks should activity B be crashed?
Number
By how many weeks should activity C be crashed?
Number
O || LO || CO
Transcribed Image Text:PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed. Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 5 $900 $1,300 В 3 $400 $500 5 $500 $675 D 3 $900 $1,200 A E 3 $1,500 $2,400 C F 3 2 $600 $700 В What is the duration of the project (in weeks)? Number What is the target duration of the project (after crashing the project)? Number By how many weeks should activity A be crashed? Number By how many weeks should activity B be crashed? Number By how many weeks should activity C be crashed? Number O || LO || CO
By how many weeks should activity C be crashed?
Number
By how many weeks should activity D be crashed?
Number
By how many weeks should activity E be crashed?
Number
By how many weeks should activity F be crashed?
Number
What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)
Number
Transcribed Image Text:By how many weeks should activity C be crashed? Number By how many weeks should activity D be crashed? Number By how many weeks should activity E be crashed? Number By how many weeks should activity F be crashed? Number What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.) Number
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.