please help, project management 1. Considered the following table. All estimated duration times are in days, and the network proceeds from Node 1 to Node 7: the picture info is downloaded below for this part a) Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. b) Identify ALL of the paths on the network diagram and note how long they are. c) What is the critical path for this project and how long is it? d) What is the shortest possible time needed to complete this project?
please help, project management
1. Considered the following table. All estimated duration times are in days, and the network proceeds from Node 1 to Node 7: the picture info is downloaded below for this part
a) Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
b) Identify ALL of the paths on the network diagram and note how long they are.
c) What is the critical path for this project and how long is it?
d) What is the shortest possible time needed to complete this project?
2. Enter the information from the previous task into MS Project. View the network diagram and critical task report to see the critical path. Generate the network diagram view and critical task report.
![The table provides details of various activities involved in a project, illustrating their initial and final nodes as well as the estimated duration for each task. Here is a breakdown of the table:
| **Activity** | **Initial Node** | **Final Node** | **Estimated Duration** |
|--------------|------------------|----------------|------------------------|
| A | 1 | 2 | 2 |
| B | 1 | 3 | 2 |
| C | 1 | 4 | 3 |
| D | 2 | 5 | 4 |
| E | 2 | 3 | 2 |
| F | 3 | 5 | 5 |
| G | 4 | 6 | 3 |
| H | 5 | 6 | 6 |
| I | 5 | 7 | 3 |
| J | 6 | 7 | 2 |
### Explanation:
- **Activity**: Each activity is represented by a unique letter (A to J).
- **Initial Node**: Specifies the starting point of the activity.
- **Final Node**: Indicates the ending point of the activity.
- **Estimated Duration**: Provides the time estimated to complete each activity.
This table is a crucial component for project management, particularly in critical path method (CPM) analysis, which helps in planning and coordinating project activities.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fb5a034dd-4ec7-43f8-b8db-0b454d82b784%2F1e794fe5-96aa-496c-b2c1-5f51aa5aa9f1%2Fk5gj9td_processed.jpeg&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![ENGR.ECONOMIC ANALYSIS](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9780190931919/9780190931919_smallCoverImage.gif)
![Principles of Economics (12th Edition)](https://www.bartleby.com/isbn_cover_images/9780134078779/9780134078779_smallCoverImage.gif)
![Engineering Economy (17th Edition)](https://www.bartleby.com/isbn_cover_images/9780134870069/9780134870069_smallCoverImage.gif)
![ENGR.ECONOMIC ANALYSIS](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9780190931919/9780190931919_smallCoverImage.gif)
![Principles of Economics (12th Edition)](https://www.bartleby.com/isbn_cover_images/9780134078779/9780134078779_smallCoverImage.gif)
![Engineering Economy (17th Edition)](https://www.bartleby.com/isbn_cover_images/9780134870069/9780134870069_smallCoverImage.gif)
![Principles of Economics (MindTap Course List)](https://www.bartleby.com/isbn_cover_images/9781305585126/9781305585126_smallCoverImage.gif)
![Managerial Economics: A Problem Solving Approach](https://www.bartleby.com/isbn_cover_images/9781337106665/9781337106665_smallCoverImage.gif)
![Managerial Economics & Business Strategy (Mcgraw-…](https://www.bartleby.com/isbn_cover_images/9781259290619/9781259290619_smallCoverImage.gif)