A construction contractor has undertaken a job with 7 major tasks. Some of the tasks can begin at any time, but others have predecessors that must be completed first. The following table shows these predecessor task numbers, together with the minimum and maximum time (in days) allowed for each task, and the total cost that would be associated with accomplishing each task in its minimum and maximum times (more time usually saves expense) Min time Max time Min cost Max cost Predecessor tasks 6. 12 1600 1000 None 8. 16 2400 1800 None 3 16 24 2900 2000 2 4 14 20 1900 1300 1,2 5 4 16 3800 2000 3 6 12 16 2900 2200 3 7 2 12 1300 800 4 The contractor seeks a way to complete all work in 40 days at least total cost, assuming that the cost of each task is linearly interpolated from times between the minimum and maximum. 1. Formulate an algebraic linear programming model of this time/cost planning problem using the decision variables (j = 1,...,7) s; : start time of taks j (in days) t; : days to complete task j.

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question
I need the answer as soon as possible
A construction contractor has undertaken a job with 7 major tasks. Some of the tasks can begin at
any time, but others have predecessors that must be completed first. The following table shows these
predecessor task numbers, together with the minimum and maximum time (in days) allowed for each task,
and the total cost that would be associated with accomplishing each task in its minimum and maximum
times (more time usually saves expense)
Min time Max time Min cost Max cost Predecessor
tasks
None
1000
1800
12
1600
2
8
16
2400
None
16
24
2900
1900
2000
2
14
20
1300
1,2
4
16
16
3800
2000
3
12
2900
2200
3
7
2
12
1300
800
The contractor seeks a way to complete all work in 40 days at least total cost, assuming that the cost of
each task is linearly interpolated from times between the minimum and maximum.
1. Formulate an algebraic linear programming model of this time/cost planning problem using the
decision variables (j = 1,...,7)
sj : start time of taks j (in days)
t; : days to complete task j.
Your model should have an objective function summing interpolated cost and main constraints to
enforce precedence relationships and the time limit.
2. Enter and solve your model in GAMS. Your GAMS model should be algebraic.
Transcribed Image Text:A construction contractor has undertaken a job with 7 major tasks. Some of the tasks can begin at any time, but others have predecessors that must be completed first. The following table shows these predecessor task numbers, together with the minimum and maximum time (in days) allowed for each task, and the total cost that would be associated with accomplishing each task in its minimum and maximum times (more time usually saves expense) Min time Max time Min cost Max cost Predecessor tasks None 1000 1800 12 1600 2 8 16 2400 None 16 24 2900 1900 2000 2 14 20 1300 1,2 4 16 16 3800 2000 3 12 2900 2200 3 7 2 12 1300 800 The contractor seeks a way to complete all work in 40 days at least total cost, assuming that the cost of each task is linearly interpolated from times between the minimum and maximum. 1. Formulate an algebraic linear programming model of this time/cost planning problem using the decision variables (j = 1,...,7) sj : start time of taks j (in days) t; : days to complete task j. Your model should have an objective function summing interpolated cost and main constraints to enforce precedence relationships and the time limit. 2. Enter and solve your model in GAMS. Your GAMS model should be algebraic.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education