Percent Completed Tons of Pulp Materials Labor and Overhead Work in process, June 1..... 20,000 90% 80% Work in process, June 30 30,000 60% 40% Started into production during June 190,000 .....
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Highlands Company uses the weighted-average method in its
Required:
1. Compute the number of tons of pulp completed and transferred out during June.
2. Compute the equivalent units of production for materials and for labor and
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images