On July 1, 2017, Cusak Construction Company Inc. contracted to build an office building for Candy Lane Corp. for a total contract price of $2,150,000. On July 1, Cusak estimated that it would take between two and three years to complete the building. In October 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Candy Lane in 2017, 2018, and 2019. 2017 340,000 1,360,000 590,000 2018 1,150,000 1,150,000 4,000,000 2019 2,400,000 Costs incurred to date (cumulative) Estimated costs to complete Billings to-Candy Lane 2,100,000 Required: Using the percentage of completion method, calculate the revenue and profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. The company used the cost-to-cost method to estimate the percentage complete.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Question 1
On July 1, 2017, Cusak Construction Company Inc. contracted to build an office building for Candy Lane
Corp. for a total contract price of $2,150,000. On July 1, Cusak estimated that it would take between two
and three years to complete the building. In October 2019, the building was deemed substantially
completed. Following are accumulated contract costs incurred, estimated costs to complete the contract,
and accumulated billings to Candy Lane in 2017, 2018, and 2019.
2019
2,400,000
Costs incurred to date (cumulative)
Estimated costs to complete
Billings to Candy Lane
2017
340,000
1,360,000
590,000
2018
1,150,000
1,150,000
1,000,000
2,100,000
Required:
Using the percentage of completion method, calculate the revenue and profit or loss to be recognized as
a result of this contract for the years ended December 31, 2017, 2018, and 2019. The company used the
cost-to-cost method to estimate the percentage complete.
Transcribed Image Text:Question 1 On July 1, 2017, Cusak Construction Company Inc. contracted to build an office building for Candy Lane Corp. for a total contract price of $2,150,000. On July 1, Cusak estimated that it would take between two and three years to complete the building. In October 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Candy Lane in 2017, 2018, and 2019. 2019 2,400,000 Costs incurred to date (cumulative) Estimated costs to complete Billings to Candy Lane 2017 340,000 1,360,000 590,000 2018 1,150,000 1,150,000 1,000,000 2,100,000 Required: Using the percentage of completion method, calculate the revenue and profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. The company used the cost-to-cost method to estimate the percentage complete.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education