On January 1, 2021, MARCOS Company entered into a contract for the construction of a building at an original price of P2,000,000 to be completed on June 30, 2023 subject to penalty of P500,000 on the it becomes virtually certain that construction will not be completed on the date agreed upon. On January 1, 2022, the contract price increased by P2,500,000 due to the change in the design of the building requested by the customer. year 12/31/2021 12/31/2022 12/31/2023 Cumulative costs incurred as of the end of the year Estimated remaining cost to complete at the end of the year 600,000 900,000 3,075,000 1,025,000 3,780,000 420,000 What is the realized gross profit (loss) to be recognized by MARCOS Company for the year ended December 31, 2023 if the outcome of construction can be estimated reliably?

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
100%
On January 1, 2021, MARCOS Company entered into a contract for the construction of a building at an
original price of P2,000,000 to be completed on June 30, 2023 subject to penalty of P500,000 on the year
it becomes virtually certain that construction will not be completed on the date agreed upon. On January 1,
2022, the contract price increased by P2,500,000 due to the change in the design of the building requested
by the customer.
12/31/2021 12/31/2022 12/31/2023
Cumulative costs incurred as of the end of the year
600,000
900,000
3,075,000
1,025,000
3,780,000
420,000
Estimated remaining cost to complete at the end of the year
What is the realized gross profit (loss) to be recognized by MARCOS Company for the year ended December 31, 2023 if the
outcome of construction can be estimated reliably?
Transcribed Image Text:On January 1, 2021, MARCOS Company entered into a contract for the construction of a building at an original price of P2,000,000 to be completed on June 30, 2023 subject to penalty of P500,000 on the year it becomes virtually certain that construction will not be completed on the date agreed upon. On January 1, 2022, the contract price increased by P2,500,000 due to the change in the design of the building requested by the customer. 12/31/2021 12/31/2022 12/31/2023 Cumulative costs incurred as of the end of the year 600,000 900,000 3,075,000 1,025,000 3,780,000 420,000 Estimated remaining cost to complete at the end of the year What is the realized gross profit (loss) to be recognized by MARCOS Company for the year ended December 31, 2023 if the outcome of construction can be estimated reliably?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education