8. On January 1, 2018, Liquid Company accepted a long-term construction project for an initial contract price of P2,000,000 to be completed on June 30, 2020. On January 1, 2019, the contract price was increased to P3,000,000 by reason of change in the design of the project. The outcome of the construction contract can be estimated reliably. The project was completed on December 31, 2020 which resulted to penalty amounting to P400,000. The entity provided the following data concerning the direct costs related to the said project for 2018 and 2019: 2019 2018 Costs during the year 880,000 1,360,000 Remaining estimated costs to complete at year- 1,320,000 560,000 end
8. On January 1, 2018, Liquid Company accepted a long-term construction project for an initial contract price of P2,000,000 to be completed on June 30, 2020. On January 1, 2019, the contract price was increased to P3,000,000 by reason of change in the design of the project. The outcome of the construction contract can be estimated reliably. The project was completed on December 31, 2020 which resulted to penalty amounting to P400,000. The entity provided the following data concerning the direct costs related to the said project for 2018 and 2019: 2019 2018 Costs during the year 880,000 1,360,000 Remaining estimated costs to complete at year- 1,320,000 560,000 end
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question

Transcribed Image Text:8. On January 1, 2018, Liquid Company accepted a long-term construction project for an initial
contract price of P2,000,000 to be completed on June 30, 2020. On January 1, 2019, the
contract price was increased to P3,000,000 by reason of change in the design of the project.
The outcome of the construction contract can be estimated reliably. The project was completed
on December 31, 2020 which resulted to penalty amounting to P400,000. The entity provided
the following data concerning the direct costs related to the said project for 2018 and 2019:
2019
2018
Costs during the year
Remaining estimated costs to complete at year-
880,000
1,360,000
1,320,000
560,000
end
What is the construction revenue for the year ended December 31, 2018?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you


Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,

Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,


Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,

Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON

Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education