On January 1, 2018, Star Construction Company entered into a contract with KC Company to build a studio house. At that time, Star Company estimated that it would take three years and would cost them P7.2M to complete the project. The contract price is P9.2M. During 2019, Star Construction Company incurred P2,392,000 in construction costs but due to rising materials and labor costs, the outcome of the contract cannot be estimated reliably in 2019. However, at the end of 2020, Engr. Richard was certain that the total costs of the project will not exceed P9.2M. KC Company was billed 25% of the contract price in 2019. 21. The profit that should be recognized in 2019 is: a. P664,444 h. (P92,000) C. PO d. P2.3M project with a fixed contract

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Please answer No. 14 and 15 as well as No. 21

Provide a complete solution thank you

Ist Centro Realty Corporation entered into a fixed price contract with Camela
Homes on July 1, 2018 to construct a medium rise condominium. At that time, 1st
Centro Realty Corporation estimated that it would take between 2 to 3 years to
complete the project. The total contract price for construction of the building is
P4,500,000. 1st Centro accounts for this contract under the percentage of
completion method. The building was deemed substantially completed on
December 31, 2020. Estimated percentage of completion, accumulated contract
costs incurred, estimated costs to complete the contract and accumulated billings
under the contract were as follows:
2018
2019
2020
% of completion
Contract costs incurred
Est. costs to complete
Progress billings
30%
60%
100%
C0.0 P1,140,000
CO0.0 P2,660,000
c00o P1,600,000
000000
P2,820,000
P1,880,000
P2,700,000
P4,800,000
P4,500,000
14. The amount of (1) Contract Revenue, (2) Cost of construction, (3) Gross Profit to
appear in the income statement for the period ended December 31, 2020 is:
(1)
P1,350,000
P1,350,000
P2,700,000
P1,880,000
(2)
P1,680,000
P1,760,000
P2,820,000
P1,980,000
(3)
(P330,000)
(P410,000)
(P120,000)
(P100,000)
a.
b.
C.
d.
ll
niub
15. The balance of the Contract Asset account on December 31, 2020 is
P3,960,000
b.
dol
P4,170,000
P2,700,000
C.
a.
d.
P4,500,000 or zero
Transcribed Image Text:Ist Centro Realty Corporation entered into a fixed price contract with Camela Homes on July 1, 2018 to construct a medium rise condominium. At that time, 1st Centro Realty Corporation estimated that it would take between 2 to 3 years to complete the project. The total contract price for construction of the building is P4,500,000. 1st Centro accounts for this contract under the percentage of completion method. The building was deemed substantially completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract and accumulated billings under the contract were as follows: 2018 2019 2020 % of completion Contract costs incurred Est. costs to complete Progress billings 30% 60% 100% C0.0 P1,140,000 CO0.0 P2,660,000 c00o P1,600,000 000000 P2,820,000 P1,880,000 P2,700,000 P4,800,000 P4,500,000 14. The amount of (1) Contract Revenue, (2) Cost of construction, (3) Gross Profit to appear in the income statement for the period ended December 31, 2020 is: (1) P1,350,000 P1,350,000 P2,700,000 P1,880,000 (2) P1,680,000 P1,760,000 P2,820,000 P1,980,000 (3) (P330,000) (P410,000) (P120,000) (P100,000) a. b. C. d. ll niub 15. The balance of the Contract Asset account on December 31, 2020 is P3,960,000 b. dol P4,170,000 P2,700,000 C. a. d. P4,500,000 or zero
On January 1, 2018, Star Construction Company entered into a contract with KC
Company to build a studio house. At that time, Star Company estimated that it
would take three years and would cost them P7.2M to complete the project. The
contract price is P9.2M. During 2019, Star Construction Company incurred
P2,392,000 in construction costs but due to rising materials and labor costs, the
outcome of the contract cannot be estimated reliably in 2019. However, at the end
of 2020, Engr. Richard was certain that the total costs of the project will not exceed
P9.2M. KC Company was billed 25% of the contract price in 2019.
21. The profit that should be recognized in 2019 is:
C.
PO
P664,444
(P92,000)
a.
d.
P2.3M
b.
ion work on a project with a fixed contract
Transcribed Image Text:On January 1, 2018, Star Construction Company entered into a contract with KC Company to build a studio house. At that time, Star Company estimated that it would take three years and would cost them P7.2M to complete the project. The contract price is P9.2M. During 2019, Star Construction Company incurred P2,392,000 in construction costs but due to rising materials and labor costs, the outcome of the contract cannot be estimated reliably in 2019. However, at the end of 2020, Engr. Richard was certain that the total costs of the project will not exceed P9.2M. KC Company was billed 25% of the contract price in 2019. 21. The profit that should be recognized in 2019 is: C. PO P664,444 (P92,000) a. d. P2.3M b. ion work on a project with a fixed contract
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education