Nadeem BSC is a civil engineering company. It started work on to civil engineering projects during the year ended 31 December 2020. The nature of both contracts is that the customer controls the asset as the project goes forward. Work is certified by a surveyor as performance obligations are completed. The following figures relate to those projects at the end of the reporting period. Qadim Bypass Hidd Mall BD’000 BD’000 Contract Price 18,000 16,000 Costs incurred to date 2,800 5,800 Estimated costs to completion 11,200 10,400 Value of work certified to date 5,600 6,000 Progress billing 5,200 6,800 An old disused oil well has been discovered under the site for the Hidd Mall and the costs of dealing with this have been taken into account in the calculation of estimated costs to completion. Nadeem BSC’s lawyers are reasonably confident that the customer will have to bear the additional costs which will be incurred in stabilising the land. If negotiations are successful, then the contract price will increase to BD10 million. Nadeem BSC recognises revenues and profits on civil engineering contracts on the basis of work certified to date. Required Calculate the figures which would appear in Nadeem BSC’s financial statements in respect of these two projects. Note correction in the question: (New price would be BD20 million not BD10 million) "If negotiations are successful, then the contract price will increase to BD20 million."
Nadeem BSC is a civil engineering company. It started work on to civil engineering projects during the year ended 31 December 2020. The nature of both contracts is that the customer controls the asset as the project goes forward. Work is certified by a surveyor as performance obligations are completed. The following figures relate to those projects at the end of the reporting period.
Qadim Bypass |
Hidd Mall |
|
BD’000 |
BD’000 |
|
Contract Price |
18,000 |
16,000 |
Costs incurred to date |
2,800 |
5,800 |
Estimated costs to completion |
11,200 |
10,400 |
Value of work certified to date |
5,600 |
6,000 |
Progress billing |
5,200 |
6,800 |
An old disused oil well has been discovered under the site for the Hidd Mall and the costs of dealing with this have been taken into account in the calculation of estimated costs to completion. Nadeem BSC’s lawyers are reasonably confident that the customer will have to bear the additional costs which will be incurred in stabilising the land. If negotiations are successful, then the contract price will increase to BD10 million.
Nadeem BSC recognises revenues and profits on civil engineering contracts on the basis of work certified to date.
Required
Calculate the figures which would appear in Nadeem BSC’s financial statements in respect of these two projects.
Note correction in the question: (New price would be BD20 million not BD10 million)
"If negotiations are successful, then the contract price will increase to BD20 million."
Step by step
Solved in 2 steps