n the job, calculate the weight of cement, moist gravel, moist sand, and water that should be added to the batch. Summarize and total the mix design when finished.
You are working on a concrete mix design that requires each cubic yard of concrete to have a 0.43 water-cement ratio, 2077 lb/yd³ of dry gravel, 244 lb/yd³ of water, and 4% air content. The available gravel has a specific gravity of Gravel = 2.60, a moisture content of 2.3%, and absorption of 4.5%. The available sand has a
specific gravity of Grand 2.40, a moisture content of 2.2%, and absorption of
1.7%. Air entrainer is to be included using the manufacturers specification of 0.1 fl.
oz/1% air/100 lb cement.
For each cubic yard of concrete needed on the job, calculate the weight of cement,
moist gravel, moist sand, and water that should be added to the batch. Summarize
and total the mix design when finished.
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 10 images