Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Activity Cost Pool Production $259,200 Setup 55,000 Materials handling 9,750 Inspection 60,000 Product engineering 123,200 Total $507,150 The activity bases identified for each activity are as follows: Activity Activity Base Production Machine hours Setup Number of setups Materials handling Number of parts Inspection Number of inspection hours Product engineering Number of engineering hours The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows: Machine Hours Number of Setups Number of Parts Number of Inspection Hours Number of Engineering Hours Units Alpha 1,440 75 65 400 125 1,800 Beta 1,080 165 80 300 175 1,350 Omega 720 310 180 500 140 900 Total 3,240 550 325 1,200 440 4,050 Each product requires 48 minutes per unit of machine time. Required: If required, round all per unit amounts to the nearest cent. 1. Determine the activity rate for each activity.
Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory
Activity | Activity Cost Pool | |||
Production | $259,200 | |||
Setup | 55,000 | |||
Materials handling | 9,750 | |||
Inspection | 60,000 | |||
Product engineering | 123,200 | |||
Total | $507,150 |
The activity bases identified for each activity are as follows:
Activity | Activity Base |
Production | Machine hours |
Setup | Number of setups |
Materials handling | Number of parts |
Inspection | Number of inspection hours |
Product engineering | Number of engineering hours |
The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows:
Machine Hours | Number of Setups | Number of Parts | Number of Inspection Hours | Number of Engineering Hours | Units | |||||||||||
Alpha | 1,440 | 75 | 65 | 400 | 125 | 1,800 | ||||||||||
Beta | 1,080 | 165 | 80 | 300 | 175 | 1,350 | ||||||||||
Omega | 720 | 310 | 180 | 500 | 140 | 900 | ||||||||||
Total | 3,240 | 550 | 325 | 1,200 | 440 | 4,050 |
Each product requires 48 minutes per unit of machine time.
Required:
If required, round all per unit amounts to the nearest cent.
1. Determine the activity rate for each activity.
Step by step
Solved in 4 steps