Mark Tuan, the Production Manager at MT Mills, can currently expect his operation to produce 1000 square yards of fabric for each ton of raw cotton. Each ton of raw cotton requires 5 labor hours to process. He believes that he can buy a better-quality raw cotton, which will enable him to produce 1200 square yards per ton of raw cotton with the same labor hours. What will be the impact on productivity (measured in square yards per labor-hour) if he purchases the higher quality raw cotton? You are required to calculate: a) Productivity for the current raw cotton? b) The new productivity if Mark Tuan use the new raw cotton. c) What is the percentage increase in productivity?
Mark Tuan, the
1000 square yards of fabric for each ton of raw cotton. Each ton of raw cotton requires 5 labor
hours to process. He believes that he can buy a better-quality raw cotton, which will enable him
to produce 1200 square yards per ton of raw cotton with the same labor hours.
What will be the impact on productivity (measured in square yards per labor-hour) if he
purchases the higher quality raw cotton?
You are required to calculate:
a) Productivity for the current raw cotton?
b) The new productivity if Mark Tuan use the new raw cotton.
c) What is the percentage increase in productivity?
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images