Manufacturing Cycle Efficiency CFA Company keeps careful track of the time related to orders and their production. During the most recent quarter, the following average times were recorded for each unit or order: Inspection time Process time Queue time Move time Wait time 2 days 4 days 6 days 8 days 10 days REQUIRED: A) How long in days is the manufacturing cycle time or throughput time? B) What is the manufacturing cycle efficiency ratio? C) What percentage of the production time is spent on non-value-added activities? D) How long in days is the delivery cycle time?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
4. Manufacturing Cycle Efficiency
CFA Company keeps careful track of the time related to orders and their production. During the most
recent quarter, the following average times were recorded for each unit or order:
Inspection time
Process time
Queue time
Move time
Wait time
2 days
4 days
6 days
8 days
10 days
REQUIRED:
A) How long in days is the manufacturing cycle time or throughput time?
B) What is the manufacturing cycle efficiency ratio?
C) What percentage of the production time is spent on non-value-added activities?
D) How long in days is the delivery cycle time?
Transcribed Image Text:4. Manufacturing Cycle Efficiency CFA Company keeps careful track of the time related to orders and their production. During the most recent quarter, the following average times were recorded for each unit or order: Inspection time Process time Queue time Move time Wait time 2 days 4 days 6 days 8 days 10 days REQUIRED: A) How long in days is the manufacturing cycle time or throughput time? B) What is the manufacturing cycle efficiency ratio? C) What percentage of the production time is spent on non-value-added activities? D) How long in days is the delivery cycle time?
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.