Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25 percent capacity cushion is best. Pi Demand Forecast Component A B C Time Standard Processing (hr/unit) 0.04 0.20 0.05 Setup (hr/lot) 1.0 4.4 8.5 Lot Size (units/lot) 50 75 100 Demand Forecast Pessimistic 16,000 10,000 18,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.) Pessimistic Expected Optimistic Capacity Requirement (M) Expected Optimistic 17,000 27,000 12,000 17,000 24,000 35,000 machines machines machines

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a
machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the
time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand
forecasts (pessimistic, expected, and optimistic). The manager believes that a 25 percent capacity cushion is best.
D
Demand Forecast
Component
A
B
C
Time Standard
Processing Setup
(hr/unit) (hr/lot)
0.04
1.0
0.20
4.4
0.05
8.5
Lot Size
(units/lot)
50
75
100
Demand Forecast
Pessimistic
Expected
Optimistic
Pessimistic
16,000
10,000
18,000
a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up
to the next whole number.)
Capacity
Requirement (M)
Expected
17,000
12,000
24,000
machines
machines
machines
Optimistic
27,000
17,000
35,000
Transcribed Image Text:Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25 percent capacity cushion is best. D Demand Forecast Component A B C Time Standard Processing Setup (hr/unit) (hr/lot) 0.04 1.0 0.20 4.4 0.05 8.5 Lot Size (units/lot) 50 75 100 Demand Forecast Pessimistic Expected Optimistic Pessimistic 16,000 10,000 18,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.) Capacity Requirement (M) Expected 17,000 12,000 24,000 machines machines machines Optimistic 27,000 17,000 35,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.