Larkin Industries manufactures several lines of decorative and functional metal items. The most recent order has been for 1200 door lock units for an apartment complex developer. The sales and production departments must work together to determine delivery schedules. Each lock unit consists of three components: the knob and face plate, the actual lock itself, and a set of two keys. Although the processes used in the manufacture of the three components vary, there are three areas where the production manager is concerned about the availability of resources. These three areas, their usage by the three components, and their availability are detailed in the table. Resource Knob and Plate Lock Key (each) Available Brass Alloy 12 5 1 15000 units Machining 18 20 10 36000 minutes Finishing 15 5 1 12000 minutes A quick look at the amounts available confirms that Larkin does not have the resources to fill this contract. A subcontractor, who can make an unlimited number of each of the three components, quotes the prices below. Component Subcontractor Cost Larkin Cost Knob and Plate 10.00 6.00 Lock 9.00 4.00 Keys (set of 2) 1.00 .50 Develop a linear programming model that would tell Larkin how to fill the order for 1200 lock sets at the minimum cost. Submit Excel Document with Your Template BELOW IS A PICTURE OF THE QUESTION TO MAKE IT EASIER
Larkin Industries manufactures several lines of decorative and
Resource Knob and Plate Lock Key (each) Available Brass Alloy 12 5 1 15000 units Machining 18 20 10 36000 minutes Finishing 15 5 1 12000 minutes
A quick look at the amounts available confirms that Larkin does not have the resources to fill this contract. A subcontractor, who can make an unlimited number of each of the three components, quotes the prices below.
Component Subcontractor Cost Larkin Cost Knob and Plate 10.00 6.00 Lock 9.00 4.00 Keys (set of 2) 1.00 .50
Develop a linear programming model that would tell Larkin how to fill the order for 1200 lock sets at the minimum cost.
Submit Excel Document with Your Template
BELOW IS A PICTURE OF THE QUESTION TO MAKE IT EASIER
![Larkin Industries manufactures several lines of decorative and functional metal items. The most recent
order has been for 1200 door lock units for an apartment complex developer. The sales and production
departments must work together to determine delivery schedules. Each lock unit consists of three
components: the knob and face plate, the actual lock itself, and a set of two keys. Although the processes
used in the manufacture of the three components vary, there are three areas where the production manager
is concerned about the availability of resources. These three areas, their usage by the three components, and
their availability are detailed in the table.
Knob and Plate
Lock
Key (each)
Available
15000 units
36000 minutes
12000 minutes
Resource
Brass Alloy
Machining
Finishing
12
1
18
20
10
15
1
A quick look at the amounts available confirms that Larkin does not have the resources to fill this contract.
A subcontractor, who can make an unlimited number of each of the three components, quotes the prices
below.
Larkin Cost
6.00
Subcontractor Cost
Component
Knob and Plate
10.00
Lock
9.00
4.00
Keys (set of 2)
1.00
.50
Develop a linear programming model that would tell Larkin how to fill the order for 1200 lock sets at the
minimum cost.
Submit Excel Document with Your Template](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fda575fa9-ca9b-498e-bac3-ed5779bd3599%2Faf1cf07b-8c39-46cb-8f1d-9854b17f169e%2Fa6r3qh_processed.png&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![MATLAB: An Introduction with Applications](https://www.bartleby.com/isbn_cover_images/9781119256830/9781119256830_smallCoverImage.gif)
![Probability and Statistics for Engineering and th…](https://www.bartleby.com/isbn_cover_images/9781305251809/9781305251809_smallCoverImage.gif)
![Statistics for The Behavioral Sciences (MindTap C…](https://www.bartleby.com/isbn_cover_images/9781305504912/9781305504912_smallCoverImage.gif)
![MATLAB: An Introduction with Applications](https://www.bartleby.com/isbn_cover_images/9781119256830/9781119256830_smallCoverImage.gif)
![Probability and Statistics for Engineering and th…](https://www.bartleby.com/isbn_cover_images/9781305251809/9781305251809_smallCoverImage.gif)
![Statistics for The Behavioral Sciences (MindTap C…](https://www.bartleby.com/isbn_cover_images/9781305504912/9781305504912_smallCoverImage.gif)
![Elementary Statistics: Picturing the World (7th E…](https://www.bartleby.com/isbn_cover_images/9780134683416/9780134683416_smallCoverImage.gif)
![The Basic Practice of Statistics](https://www.bartleby.com/isbn_cover_images/9781319042578/9781319042578_smallCoverImage.gif)
![Introduction to the Practice of Statistics](https://www.bartleby.com/isbn_cover_images/9781319013387/9781319013387_smallCoverImage.gif)