L4L lol-sizng rule, develop a Material Requirements Plan (MRP) Jor the n 8 weeks for A151 part. Item: A151 Week Lot size: L4L 4 5 6. 7 8 Lead time: 1 Gross Requirements Scheduled Receipts On Hand Inventory Net Requirements Planned Order Receipts Planned Order Releases
L4L lol-sizng rule, develop a Material Requirements Plan (MRP) Jor the n 8 weeks for A151 part. Item: A151 Week Lot size: L4L 4 5 6. 7 8 Lead time: 1 Gross Requirements Scheduled Receipts On Hand Inventory Net Requirements Planned Order Receipts Planned Order Releases
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![1.
Speedy, Inc. is a company that produces automotive electrical components. A151 is a
common part for all its products. Consider the following gross requirements and inventory
data for A151 part:
Week
[Gross requirements
1
3
4
5
6
7
30
40
30
70
20
Inventory Data:
Lead time
Beginning inventory
Scheduled receipts
Holding cost
[Setup cost
1 week
40
$2.50/unit/week
$150
(i)
Based on the L4L lot-sizing rule, develop a Material Requirements Plan (MRP) for the next
8 weeks for A151 part.
Item: A151
Week
Lot size: L4L
3
4
6
8
Lead time: 1
Gross Requirements
Scheduled Receipts
On Hand Inventory
Net Requirements
Planned Order Receipts
Planned Order Releases](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F24256a1a-a00a-465f-89af-08079fe689cd%2F38ef2c7a-8cc8-45d3-9d81-707ec4380d16%2Figtdl_processed.png&w=3840&q=75)
Transcribed Image Text:1.
Speedy, Inc. is a company that produces automotive electrical components. A151 is a
common part for all its products. Consider the following gross requirements and inventory
data for A151 part:
Week
[Gross requirements
1
3
4
5
6
7
30
40
30
70
20
Inventory Data:
Lead time
Beginning inventory
Scheduled receipts
Holding cost
[Setup cost
1 week
40
$2.50/unit/week
$150
(i)
Based on the L4L lot-sizing rule, develop a Material Requirements Plan (MRP) for the next
8 weeks for A151 part.
Item: A151
Week
Lot size: L4L
3
4
6
8
Lead time: 1
Gross Requirements
Scheduled Receipts
On Hand Inventory
Net Requirements
Planned Order Receipts
Planned Order Releases
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 7 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.