KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material-Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor - Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost - Actual variable overhead costs were $42,000 allocated on direct labor hours dele ksp Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. KAYAK Corporation makes a kayak with the following standard costs per unit produced Standard Quantity/Efficiency 3.5 lbs per unit produced 1.25 hrs per unit produced 1.25 hrs per unit produced Direct Materials Direct Labor Mfg OH Actual Results: 12,250 units produced Direct material-Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Show Transcribed Text Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance Standard Price/Rate Direct Materials Direct Labor Mfg OH $3.50 per lb $20.00 per hr $3.10 per hr KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
icon
Concept explainers
Topic Video
Question
KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit
produced Standard Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced
$3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of
$131,250. Direct Labor - Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost - Actual variable
overhead costs were $42,000 allocated on direct labor hours dele ksp Required: a. Compute total production costs, standard and actual,
and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity
variance and how much by price variance. d. Compute the total overhead cost variance and determine how much is driven by overhead.
efficiency variance and how much by rate variance c. Compute the total labor cost variance and determine how is driven by efficiency
variance and how much by rate variance.
KAYAK Corporation makes a kayak with the following standard costs per unit produced:
Standard
Quantity/Efficiency
3.5 lbs per unit produced
Standard
Price/Rate
1.25 hrs per unit produced
1.25 hrs per unit produced
Direct Materials
Direct Labor
Mfg OH
Actual Results:
12,250 units produced
Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250.
Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr.
Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor
hours
Required:
a. Compute total production costs, standard and actual, and calculate total production cost variance
b. Compute the total materials cost variance and determine how much is driven by quantity variance
and how much by price variance.
c. Compute the total labor cost variance and determine how is driven by efficiency variance and how
much by rate variance.
d. Compute the total overhead cost variance and determine how much is driven by overhead
efficiency variance and how much by rate variance
Show Transcribed Text
$3.50 per lb
$20.00 per hr.
$3.10 per hr
KAYAK Corporation makes a kayak with the following standard costs per unit produced:
Standard
Standard
Quantity/Efficiency
3.5 lbs per unit produced
Price/Rate
Direct Materials
Direct Labor
Mfg OH
Actual Results:
1.25 hrs per unit produced
1.25 hrs per unit produced
$3.50 per lb
$20.00 per hr
$3.10 per hr
12,250 units produced
Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250.
Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr.
Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor
hours
Required:
a. Compute total production costs, standard and actual, and calculate total production cost variance
b. Compute the total materials cost variance and determine how much is driven by quantity variance
and how much by price variance.
c. Compute the total labor cost variance and determine how is driven by efficiency variance and how
much by rate variance.
d. Compute the total overhead cost variance and determine how much is driven by overhead
efficiency variance and how much by rate variance
Transcribed Image Text:KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor - Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost - Actual variable overhead costs were $42,000 allocated on direct labor hours dele ksp Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. d. Compute the total overhead cost variance and determine how much is driven by overhead. efficiency variance and how much by rate variance c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate 1.25 hrs per unit produced 1.25 hrs per unit produced Direct Materials Direct Labor Mfg OH Actual Results: 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance Show Transcribed Text $3.50 per lb $20.00 per hr. $3.10 per hr KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Standard Quantity/Efficiency 3.5 lbs per unit produced Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education