In a school, there are four teachers X1,X2,X3,X4 and five batches Y1,Y2,Y3,Y4,Y5. Given that teacher Xi is required to teach batch Yj for Pij periods, schedule a complete routine in the minimum possible number of periods. The matrix is given below: X1 X2 X3 X4 Y1 2 2 -- -- Y2 1 Y3 -- -- Y4 | 1 2 1 -- Y5 1 1 -- -- Remember there are only 3 class rooms available.
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Cycle time is the total time spent to manufacture a single unit of item.
Q: A manutacturer is designing a product layout for a new product production. It plans to use a…
A: Assembly line balancing is the process of making a decision regarding assigning the task to the…
Q: E What will be the idle time for the LAST Workstation?
A: Line balancing is the process of arranging the activities to different workstations based on duck…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Cycle time is the actual total time incurred in manufacturing a product by the team members in an…
Q: What will be the idle time for the
A: Idle time for each workstation indicating the balance time after allocating all possible activities…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data; Output = 60 units Available time = 8 hrs or 8*60 = 480 min
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F 1.8 G 1.5…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data: Production line = 8 hours per day Demand = 90 units per day Task Task time Immediate…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand = 100 units Time available = 8×60= 480 minutes
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: SPT sequence: Sequence -Select- -Select- -Select- -Select- Processing Time Due Date Average How…
A: Sequencing involves deciding the order in which tasks or jobs are performed in a production or…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F…
Q: Three jobs are to be scheduled on two machines A & B . Assume that the jobs are processed in the…
A: A Gantt chart is a kind of bar chart that represents a project schedule, Gantt charts enable the…
Q: A manufacturer is designing a product layout fora new produc hours per day in order to meet…
A: Demand= 70 units Time available= 8*70= 560 minutes Cycle time= time available/ demand= 560/60= 9.3…
Q: The following table gives the operation times and due dates for i ve jobs that are to be processed…
A: JOBPROCESSINGTIMEDUE DATE(DAY)1016days51027days31034days41049days71055days2The objective is to…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Production time= 8*60= 480 minutes Demand= 100 units Cycle time= production time/ demand= 480/100=…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The flow diagram for the product is shown below.
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: bama pie company's assembly line operations (the assembly line operates for six hundred minutes per…
A: Product assembly time required to meet demand = Net available time to work / Customer demand Given…
Q: Using the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three…
A: Given-
Q: One possible solution method for the machine-to job assignment problem is the following heuristic…
A: Yes, this heuristic provides the most efficient method of task assignment because projects done on…
Q: What will be the idle time
A: Line balancing the process of allocating activities based on the cycle time and available tie…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 A B LL F E D C
A: Given the data stated below, Job Operation 1(Hours) Operation 2(Hours) A 4 8 B 10 5 C 3 11…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: A local bakery makes custom cakes for special events such as weddings and graduations. Making cakes…
A: Cake Order Baking time Decorating time A 3 4 B 1 2 C 4 7 D 2 4 E 5 10 F 2 6 G 5 7 H…
Q: A serial process has 5 steps – A (4), B(5), C(2), D(6), and E(3) – that have to be performed in this…
A: Here, I have been given a serial process, this process has five steps, and each step includes a…
Q: The single machine-scheduling problem consists of: Select one: None is correct n jobs with the same…
A: Production scheduling is an essential activity, which aims to prepare a schedule to produce a mix of…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data is Demand = 80units/day Working hours = 8
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Daily Working hour= 8 hours Daily Demand = 90 units Sum of total task time =…
Q: A ready-made dress company is manufacturing its 7 products through two stages i.e. cutting and…
A: A readymade garments manufacturer needs to process 7 items with the help of two stages of…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The efficiency can be determined as follows: Efficiency = Sum of total task timesNumber of…
Q: Job A C D E Processing time Job Due Date (Days) 24 25 17 3 7 (Days) 18 17 12 2 5 At a paint shop,…
A: JobProcessing time (days)Job due date (days)A1824B1725C1217D23E57
Q: Using the FCFS rule for scheduling, the sequence is 1-2-3. For the schedule developed using the FCFS…
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: A bank's mortgage department must process the following six jobs to maximize client satisfaction.…
A:
Q: Consider two arrival processes. The coefficient of variation of process 1 is CV1, and the…
A: The answer is True.
Q: How much total time is required to process all the seven jobs? Illustrate this using a Gant Chart.
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The flow diagram for the product is shown below.
Q: An electric cintractors record during the last five weeks indicate the number of job requests…
A: Given data
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Production time= 8*60= 480 minutes Demand= 110 units Cycle time= production time/ demand = 480/110 =…
Q: An order for 150 units is processed on work centers A and B. It is decided to over lap A and B by…
A: Manufacturing lead time is the time taken in delivering the final product to the customers. It is…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: To utilize the product layout, the complete work to be performed should be dividable into little…
Q: How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Step by step
Solved in 2 steps
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What is the idleness in percentage? a. 31.34 O b. 81.82 O c. None is the correct…A defense contractor in Dallas has six jobs awaiting processing. Processing time and due dates are given in the table. Assume that jobs arrive in the order shown. Compare the average completion time, utilization, average jobs in the system and average job lateness of the following scheduling rules. Start date is day 1. a) SPT: shortest processing time and b) EDD: earliest due dateOne possible solution method for the machine-tojob assignment problem is the following heuristic procedure. Assign the machine to job 1 that completes job 1 quickest. Then assign the machine to job 2 that, among all machines that still have some capacity, completes job 2 quickest. Keep going until a machine has been assigned to all jobs. Does this heuristic-procedure yield the optimal solution for this problem? If it does, see whether you can change the job times so that the heuristic does not yield the optimal-solution.
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A. B, C, D. E,F. and Grespectively. Task A does not have any predecessor to start. To start Task B. it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas starting task F needs the completion of both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A. B. C. D. E.F. and Gare 2.8.21,0.9.1.0, 1.2. 1.8, and 4.7 minutes respectively. How many minimum numbers of workstations are needed? Oa 3 Ob. None is the correct answer Oc 5 Od. 1 Oe 6The Safe Zone Restaurant, a 24-hour restaurant, faces changing requirements from hour to hour. More workers are needed for peak hours, and fewer are needed in between. The following table shows the worker requirement for the first 12 hours in the restaurant: Table 8. Staff Requirement at the Safe Zone Restaurant Time Period 10 11 12 1 PM|2 PM|3 PM|4 PM|5 PM|6 PM 7 PM|8 PM|9 PM АM | АM | РМ Requirement 7 Assigned On Duty Overstaffed 9 10 10 8 6 6. 8 8 12 12 8 a) You are required to apply the first-hour principle to staff each hour with the required number of cafeteria staff, showing how many staff are on duty each given hour, the number of staff you have assigned to work each hour and any overstaffing for each hour. i. Schedule the staff to work in 8-hour shifts. ii. Schedule the staff to work in 4-hour shifts. b) Indicate with at least one reason, which schedule would be more optimal from an Operations Scheduling perspective?A manufacturer is designing a product layout for a new product productionIt plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namelyABC, D, E, F, and Grespectively. Task A does not have any predecessor to startTo start Task B.it requires Task A to be completedStarting tasks needs, the task B to be completed. Also, starting task Dneeded task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed task Fto be completed. The processing times for tasks, ABC, D. E. and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8 and 4.7 minutes respectively. What should be the cycle time in minutes? a 4.7 b. None is the correct answer Oc 7.5 d6.86 e.
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to :longest task time first, the tasks that will be assigned to the FOURTH workstation are Select one .a G only…A work cell in a local manufacturer has a workstation with 4 machines that form a line (Machine 1-Machine 2-Machine 3-Machine 4). Each unit needs to pass through each machine in order to be completed. Each machine has a production capacity of four units per hour. What is the process time of the work cell in minutes per unit? 15 4 8 16A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are Select one: Oa. B and…
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? O a. 4.8 Ob. 4.4 None is the correct answer O d. 0.9 O e. 4.5In Canada, you must take 10 hours off-duty in every 24-hour period and 8 of those hours must be consecutive. How can you take the other two hours off-duty during your 16-hour workshift?A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only startupon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task Fto be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.4, 2.2,0.9, 1.0, 1.2, 1.8. are 1.5 minutes respectively. How many minimum numbers of workstations are needed? Round-up to the nearest integer O a. 8 O b. 5 Oc. None is the correct answer O d. 6 O e. 4.