In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed In 2026. Information related to the contract is as follows: 2024 $ 2,490,000 5,810,000 2,030,000 1,815,000 2025 $ 3,984,000 1,826,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 4,444,000 3,900,000 2026 $ 2,008,600 e 3,526,000 4,285,000 Problem 6-10 (Algo) Part 2 2-a. In the journal below, complete the necessary Journal entries for the year 2024 (credit "Cash, Materials, etc. for construction costs incurred). 2-b. In the journal below, complete the necessary Journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs incurred). 2-c. In the Journal below, complete the necessary Journal entries for the year 2026 (credit "Cash, Materials, etc." for construction costs incurred).

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed In 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Complete this question by entering your answers in the tabs below.
Req 2A
Problem 6-10 (Algo) Part 2
2-a. In the journal below, complete the necessary Journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs
Incurred).
View transaction list
2-b. In the journal below, complete the necessary Journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs
Incurred).
2-c. In the journal below, complete the necessary Journal entries for the year 2026 (credit "Cash, Materials, etc." for construction costs
Incurred).
Journal entry worksheet
<
1 2 3 4
2024
$ 2,490,000
5,810,000
2,030,000
1,815,000
Record construction costs.
Req 28
Req 20
In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs
incurred).
Note: If no entry is required for a transaction/event, select "No journal entry required" in the first account field.
Note: Enter debits before credits.
Date
2024
Record entry
2025
$ 3,984,000
1,826,000
General Journal
Clear entry
4,444,000
3,900,000
Debit
2026
$ 2,008, 600
e
3,526,000
4,285,000
Credit
View general journal
C
Transcribed Image Text:In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed In 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Req 2A Problem 6-10 (Algo) Part 2 2-a. In the journal below, complete the necessary Journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs Incurred). View transaction list 2-b. In the journal below, complete the necessary Journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs Incurred). 2-c. In the journal below, complete the necessary Journal entries for the year 2026 (credit "Cash, Materials, etc." for construction costs Incurred). Journal entry worksheet < 1 2 3 4 2024 $ 2,490,000 5,810,000 2,030,000 1,815,000 Record construction costs. Req 28 Req 20 In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). Note: If no entry is required for a transaction/event, select "No journal entry required" in the first account field. Note: Enter debits before credits. Date 2024 Record entry 2025 $ 3,984,000 1,826,000 General Journal Clear entry 4,444,000 3,900,000 Debit 2026 $ 2,008, 600 e 3,526,000 4,285,000 Credit View general journal C
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education