in 2021, the southgate construction company entered into a contract to construct a bridge for $12,000,000. the bridge was completed in 2023. information related to the contract is as follows: 2021 2022 2023 cost incurred during the year $1,840,000 $3,760,000 $4,500,000 estimated costs to complete as of year-end $6,160,000 $4,400,000 $0 billings during the year $3,000,000 $4,000,000 $5,000,000 cash collections during thee year $2,600,000 $3,900,000 $5,100,000 southgate recognizes revenue using the completed contract method. what amount will southgate show on the balance sheet at december 31, 2022? multiple choice costs in excess of billings (asset) $5,600,000 billings in excess of costs (liability) $1,400,000 billings in excess of costs (liability) $280,000 costs in excess of billings (asset) $280,000 If answered within one hour,it would be appreciable!! answer all questions.
in 2021, the southgate construction company entered into a contract to construct a bridge for $12,000,000. the bridge was completed in 2023. information related to the contract is as follows: 2021 2022 2023 cost incurred during the year $1,840,000 $3,760,000 $4,500,000 estimated costs to complete as of year-end $6,160,000 $4,400,000 $0 billings during the year $3,000,000 $4,000,000 $5,000,000 cash collections during thee year $2,600,000 $3,900,000 $5,100,000 southgate recognizes revenue using the completed contract method. what amount will southgate show on the balance sheet at december 31, 2022?
multiple choice
costs in excess of billings (asset) $5,600,000
billings in excess of costs (liability) $1,400,000
billings in excess of costs (liability) $280,000
costs in excess of billings (asset) $280,000
If answered within one hour,it would be appreciable!! answer all questions.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images