If the materials price variance is $3000 F and the materials quantity and labor variances are each $2700 U, what is the total materials variance? a. $2700 U. b. $300 F. c. $3150 U. d. $3000 F.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 16MC: When is the direct labor time variance favorable? A. when the actual quantity used is greater than...
icon
Related questions
Question
If the materials price variance is $3000 F and the materials quantity and labor variances are each $2700 U, what is the total materials
variance?
a. $2700 U.
b. $300 F.
c. $3150 U.
d. $3000 F.
Transcribed Image Text:If the materials price variance is $3000 F and the materials quantity and labor variances are each $2700 U, what is the total materials variance? a. $2700 U. b. $300 F. c. $3150 U. d. $3000 F.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Financial & Managerial Accounting
Financial & Managerial Accounting
Accounting
ISBN:
9781337119207
Author:
Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:
Cengage Learning